Week of Jan. 19, 2026

Haga clic aquí para ver esta informacíon en español.

Edinger Avenue Closures

WHAT:

Bridge construction activities at the Edinger Avenue bridge are ongoing, which will require closing eastbound and westbound Edinger underneath the freeway.


WHEN:

From 9 p.m. to 5 a.m. nightly, Monday, Jan. 19 through Friday, Jan. 23.


This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Southbound Dyer Road Off-Ramp

Extended Closure

WHAT:

Crews are expected to perform drainage work at the southbound SR-55 Dyer Road straight off-ramp, which will require an extended closure of the ramp. The southbound SR-55 Dyer Road loop off-ramp will remain open.


WHEN:

The off-ramp is expected to close as soon as 9 p.m., Tuesday, Jan. 27 and reopen to motorists by 5 a.m., Friday, Feb. 6.


This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Southbound McFadden Avenue Off-Ramp Extended Closure Underway

WHAT:

Crews are currently performing drainage work at the southbound SR-55 McFadden Avenue off-ramp, which requires an extended closure of the ramp and the auxiliary lane.


WHEN:

9 p.m., Tuesday, Jan. 13 through 5 a.m., Friday, Jan. 23.


This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Upcoming Retaining Wall Construction

In February, crews are expected to perform nighttime backfilling activities at the retaining wall adjacent to the northbound SR-55 McFadden Avenue off-ramp. More information will be provided in future communications.

Closures and Detours Map

Bookmark the closures and detours map for quick access to real-time construction information. Click on the construction icons to view activities and closures.

About the Project

OCTA, in cooperation with Caltrans, is improving 4 miles of SR-55 between I-405 and I-5. The project will improve traffic flow and reduce travel time by adding one regular lane and one carpool lane in each direction. Also, the project will add merge lanes between several interchanges and stripe carpool lanes for continuous access, augmenting safety on the freeway by making merging easier. These enhancements are expected to create a better, smoother driving experience for motorists.