Week of March 31, 2025

Haga clic aquí para ver esta informacíon en español.

COMING SOON: Northbound Dyer Road Loop On-Ramp Extended Closure

An extended closure of the northbound SR-55 Dyer Road loop on-ramp is expected to occur in mid-April for pavement work. Additional information will be provided in future communications. 

Northbound SR-55 Dyer Road Off-Ramp

Extended Closure

WHAT:

Crews are expected to remove and pour concrete as part of the northbound SR-55

Dyer Road off-ramp reconstruction.


WHEN:

The off-ramp is expected to close as soon as 9 p.m., Tuesday, April 1 and reopen to motorists by 5 a.m., Friday, April 11.

Dyer Bridge Pile Driving Update and Closures

To accommodate ongoing pile driving operations, crews are expected to temporarily close the outside left-turn lane on eastbound Dyer Road, as well as the outside lane on northbound Grand Avenue beginning as soon as 9 a.m., Monday, March 31 for approximately two weeks. 


In addition, crews are scheduled to relocate the pile driving crane, which will require a full closure of Dyer underneath the freeway from 9 p.m. to 5 a.m., nightly, Monday, March 31 and Tuesday, April 1.

Closures and Detours Map

Bookmark the closures and detours map for quick access to real-time construction information. Click on the construction icons to view activities and closures.

About the Project

OCTA, in cooperation with Caltrans, is improving 4 miles of SR-55 between I-405 and I-5. The project will improve traffic flow and reduce travel time by adding one regular lane and one carpool lane in each direction. Also, the project will add merge lanes between several interchanges and stripe carpool lanes for continuous access, augmenting safety on the freeway by making merging easier. These enhancements are expected to create a better, smoother driving experience for motorists.