Construction of the 3,139-foot-long Lane Channel was completed last month after being demolished in Spring 2023. Crews will continue with fence work and perform cleanup efforts along the channel.
This milestone required tremendous effort from construction crews and included activities such as installing and removing temporary shoring beams, excavation, backfilling, and concrete pours. Previously a V-shape channel, the new U-shape configuration was designed to withstand a 100-year storm while increasing stormwater capacity.
Fun fact: Seventy-six tons of concrete and 703 tons of steel were used to reconstruct this structure along southbound SR-55.
Stay in the know, and visit octa.net/55Construction to stay informed on construction progress.
|