Crews are expected to perform the following daytime and nighttime activities:
- Restriping lanes on northbound (NB) SR-55, to shift traffic toward the center median
- Placing temporary concrete barriers along the outside shoulder of NB SR-55
- Excavating for a new retaining wall on Pullman Street between MacArthur Boulevard and McGaw Avenue
- Performing electrical work along NB SR-55
- Clearing vegetation behind temporary concrete barriers within the work area
To facilitate this work, lane and ramp closures are planned on NB SR-55, nightly from 10 p.m. to 5 a.m., Monday, Oct. 3 through Friday, Oct. 7.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
|