In observance of the Presidents Day Holiday, there will be no closures from Friday, Feb. 13 through Monday, Feb. 16. Closures will resume on Tuesday, Feb. 17.
Segment 1: Lakeview to SR-55
New Lakeview Configuration Beginning March 2
Starting at 5 a.m., Monday, March 2 motorists traveling both northbound (NB) and southbound (SB) on Lakeview Avenue will use a new signalized intersection to access the westbound (WB) SR-91 straight on-ramp.
Beginningas early as 9 p.m. on March 1, the WB SR-91 loop on-ramp at Lakeview Avenue will be permanently closed.
NB motorists will turn left at the signal to access the on-ramp
SB motorists will turn right at the signal
Upcoming 55-Hour Closure
55-Hour Closure
In preparation for the new interchange configuration, crews are anticipated to perform construction activities that will require a continuous 55-hour closure starting as early as 9 p.m., Friday, Feb. 27 to 5 a.m., Monday, March 2 of the following:
WB SR-91 straight on-ramp at Lakeview Avenue
All lanes of SB Lakeview
One lane of northbound NB Lakeview
Potential impacts may include back up alarms from construction vehicles, bright lights, noise, and traffic delays.This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
More details will be provided in the following alert.
Lakeview Avenue Bridge Construction
Progress at the Lakeview Avenue Bridge
Crews are beginning to set up falsework, or temporary support structures, to prepare for the next phase of construction. In addition, crews are preparing for girder, steel support beams, installation which will occur in March 2026.
Crews preparing to place temporary structures to build the next step of the new Lakeview Avenue bridge.
Completed concrete pour for a portion of the new Lakeview Avenue bridge.
Crews placing temporary support structures for construction of the new Lakeview Avenue bridge.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Crews are expected to continue daily work on the sound wall starting as early as 7 a.m. to 4 p.m. The new sound wall along the WB SR-91 on-ramp is anticipated to be complete by mid-2026.
TONIGHT, Friday, Feb. 13 as early as 6 p.m. to 4 a.m., crews are anticipated to perform pavement grinding activities along the WB SR-91 On-Ramp at Lakeview.
Crews placing and grouting the blocks that form the top of the sound wall along the WB SR-91 on-ramp at Lakeview Avenue.
Along EB SR-91 On-Ramp at Lakeview
Crews have been forming and pouring the retaining wall along the EB SR-91 on-ramp. Crews are also making progress preparing the area for the foundation of the new bridge.
The retaining wall along the EB SR-91 on-ramp at Lakeview after concrete forms have been removed.
Crews placing structural backfill to support the foundation of the retaining wall along the EB SR-91 on-ramp at Lakeview.
Crews completing the structural backfill process to support the foundation of the retaining wall along the EB SR-91 on-ramp at Lakeview.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Segment 2: SR-55 to SR-57
Construction on Segment 2 of the SR-91 Improvement Project is expected to begin in mid-2026.
Segment 3: SR-57 Interchange
Construction on Segment 3 of the SR-91 Improvement Project is expected to begin in February 2026, bringing major upgrades to the SR-91/SR-57 interchange and surrounding areas to improve traffic flow, enhance safety, and support long-term mobility.
During the week of February 16, crews are scheduled to begin putting up construction signs within the corridor. K-rail placement and clearing and grubbing activities will follow. Additional schedule updates will be shared in upcoming alerts.
NB Lakeview Avenue between Santa Ana Canyon and WB SR-91 Off-Ramp:
Nightly, as early as 10 p.m. to 5 a.m., Tuesday, Feb. 17 through Thursday, Feb. 19 (into Friday morning)
Freeway and Ramp Closures:
Nighttime lane closures on EB and WB SR-91 will occur regularly throughout construction. At least one lane will be open to traffic at all times, unless otherwise specified.
WB SR-91 Straight On-Ramp at Lakeview Avenue
Nightly, as early as 10 p.m. to 5 a.m., Wednesday, Feb. 18 and Thursday, Feb. 19 (into Friday morning)
WB SR-91 Loop On-Ramp at Lakeview Avenue
Nightly, as early as 10 p.m. to 5 a.m., Tuesday, Feb. 17 through Thursday, Feb. 19 (into Friday morning)
EB SR-91 On-Ramp at Lakeview Avenue
Nightly, as early as 10 p.m. to 5 a.m., Tuesday, Feb. 17 through Thursday, Feb. 19 (into Friday morning)
EB SR-91 Loop On-Ramp at Lakeview (Two-Year Closure):
The two-year closure started on July 7, 2025
The schedule is subject to change due to inclement weather or unforeseen operational issues.
For a full list of weekly closures and detours, and the most up-to-date project information, please click on the projectGoogle Mapbelow.
Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.
About the Project
91 Connect Business Program
The "91 Connect: Shop Local, Support Local" program supports businesses along the SR-91 Improvement Project corridor by promoting visibility and minimizing construction impacts through proactive outreach. Business spotlights on the project website, social media, and construction alerts, are all aimed to encourage the community to shop local and raise awareness of local businesses during construction. Click here to learn more.
Overview
The SR-91 (SR-57 to SR-55) Improvement Project will improve 6.6 miles of State Route 91 (SR-91) through Anaheim, Fullerton, Orange, Placentia and Yorba Linda. The project will improve mobility throughout the corridor, reduce weaving and merging between ramps, and improve on- and off-ramps. The project will reconstruct the La Palma Avenue, Kraemer Boulevard/Glassell Street, Tustin Avenue and Lakeview Avenue bridges and interchanges with standard lanes, shoulders and sidewalks in each direction. Visit our website for more information on segment and schedule details,octa.net/91improvements.