Memorial Day
In observance of Memorial Day Holiday, there will be no closures from Friday, May 22 through Monday, May 25.
Segment 3 Virtual Webinar
Attend a virtual webinar to learn more about Segment 3 of the SR-91 Improvement Project.
Continued Nightly Lakeview Avenue Closures
Crews are anticipated to continue construction activities that will require a full Lakeview Avenue street closure between Santa Ana Canyon Road and the westbound (WB) SR-91 off-ramp at Lakeview nightly, as early as Friday, May 15 and Monday, May 18 through Thursday, May 21 (into Friday morning).
A concrete pour to form the deck of the new Lakeview Avenue bridge is expected to begin at 10 p.m. on Tuesday, May 19 and activities are expected to continue through noon on Wednesday, May 20.
Intermittent nightly closures on Lakeview Avenue are expected to continue through mid-June.
For a full list of weekly closures and detours, and the most up-to-date project information, please click on the projectGoogle Mapbelow.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Segment 1: Lakeview to SR-55
Temporary Lakeview Configuration
Motorists traveling both northbound (NB) and southbound (SB) on Lakeview Avenue will now use a new signalized intersection to access the newly realigned WB SR-91 straight on-ramp, and the WB SR-91 loop on-ramp at Lakeview Avenue has been permanently closed.
In this configuration, the eastern side of Lakeview Avenue is fully closed to pedestrians through August 2026. The western side is accessible to pedestrians.
Crews are hard at work. You may notice more traffic than usual. Please allow for extra time or utilize alternative routes.
Lakeview Avenue Bridge Construction
Crews are placing rebar and preparing for the concrete pour to form the deck of the bridge. The deck concrete pour is expected to begin at 10 p.m. on Tuesday, May 19 and activities are expected to continue through noon on Wednesday, May 20. This work may be loud.
Intermittent night work is expected to continue into late May.
Photos of concrete barrier, rebar and diaphragm work on the new Lakeview Avenue bridge.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Crews continue work on a sound wall along the WB SR-91 on-ramp and a retaining wall along the EB SR-91 on-ramp. Daily construction activities will start as early as 7 a.m. to 4 p.m. The new wall is anticipated to be complete by mid-2026.
Crews placing and grouting the blocks that form the top of the sound wall along the WB SR-91 on-ramp and placing structural backfill for the retaining wall along the EB SR-91 on-ramp.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Segment 2: SR-55 to SR-57
Construction on Segment 2 of the SR-91 Improvement Project is expected to begin in mid-2026.
Segment 3: SR-57 Interchange
State College Boulevard Construction Activities
Crews will continue striping activities and installation of temporary lighting and traffic control systems in the Segment 3 construction zone. Work will occur during both daytime and nighttime hours, with nighttime operations expected throughout much of the week. State College Boulevard will remain open to traffic; however, overnight lane reductions, ramp closures, and connector closures are required to safely complete this work.
More information will be provided in upcoming construction alerts.
Check the project Google Map for closure updates.
Crews continued overnight work in the Segment 3 construction zone, including traffic control installation and roadway preparation activities.
Nighttime lane closures on EB and WB SR-91 and NB and SB SR-57 are anticipated to occur regularly throughout construction. At least one lane will be open to traffic at all times, unless otherwise specified.
WB SR-91 Loop On-Ramp at Lakeview:
Permanently closed
EB SR-91 Loop On-Ramp at Lakeview (Two-Year Closure):
The two-year closure started on July 7, 2025
WB SR-91 State College Blvd Off-Ramp:
As early as 10 p.m., Thursday, May 21 to 5 a.m., Friday, May 22
WB SR-91 State College Blvd On-Ramp:
As early as 10 p.m., Thursday, May 21 to 5 a.m., Friday, May 22
The schedule is subject to change due to inclement weather or unforeseen operational issues.
For a full list of weekly closures and detours, and the most up-to-date project information, please click on the projectGoogle Mapbelow.
Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.
About the Project
91 Connect Business Program
Aramis Realty Group
Address: 436 N. Lakeview Ave., Anaheim Hills, CA 92807
Socials: Facebook: AramisRealtyGroup
Looking to buy, sell, or invest in California real estate? Aramis Realty Group Inc. is your trusted partner in navigating the dynamic California market. With local expertise, personalized service, and a commitment to transparency, their team helps first-time buyers, seasoned investors, and sellers achieve their real estate goals with confidence. Whether you're searching for your dream home or your next investment opportunity, Aramis Realty Group is ready to guide you every step of the way.
The "91 Connect: Shop Local, Support Local" program supports businesses along the SR-91 Improvement Project corridor by promoting visibility and minimizing construction impacts through proactive outreach. Business spotlights on the project website, social media, and construction alerts, are all aimed to encourage the community to shop local and raise awareness of local businesses during construction. Click here to learn more.
Overview
The SR-91 (SR-57 to SR-55) Improvement Project will improve 6.6 miles of State Route 91 (SR-91) through Anaheim, Fullerton, Orange, Placentia and Yorba Linda. The project will improve mobility throughout the corridor, reduce weaving and merging between ramps, and improve on- and off-ramps. The project will reconstruct the La Palma Avenue, Kraemer Boulevard/Glassell Street, Tustin Avenue and Lakeview Avenue bridges and interchanges with standard lanes, shoulders and sidewalks in each direction. Visit our website for more information on segment and schedule details,octa.net/91improvements.