In observance of the Christmas and New Year Holidays, there will be no closures on Wednesday, Dec. 24 through Sunday, Dec. 28, 2025, and on Wednesday, Dec. 31, 2025 through Sunday, Jan. 4, 2026.
The information below includes scheduled activities anticipated for Dec. 19 through Dec. 28, 2025 - our next email will be sent Friday, Jan. 2, 2026.
For the most current project closures, detours and traffic information, please view our project Google Map and use Waze. Drive safely!
The schedule is subject to change due to inclement weather or unforeseen operational issues.
⚠️ TONIGHT, DEC. 19, 2025 ⚠️
Nighttime Directional Freeway,
Street and Ramp Closures
WHAT:
TONIGHT, Dec. 19, crews are expected to close westbound (WB) SR-91 from the WB off-ramp at Lakeview Avenue to SR-55, northbound (NB) Lakeview Avenue, and the inside lane of WB Santa Ana Canyon Road, leaving one lane open for motorists.
The full directional closure of WB SR-91 is necessary to restripe lanes and replace crash cushions along this stretch of freeway for safety purposes. The full directional closure of NB Lakeview is closed for bridge work preparation.
The eastbound (EB) and WB SR-91 off-ramps at Lakeview will remain open.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
WHEN:
As early as TONIGHT, 10 p.m., Friday, Dec. 19 to 5 a.m., Saturday, Dec. 20
CLOSURES:
WB SR-91 from WB off-ramp at Lakeview Avenue to SR-55
NB Lakeview from WB SR-91 off-ramp to Santa Ana Canyon Road
WB SR-91 connector to southbound (SB) SR-55
EB/WB SR-91 on-ramps at Lakeview
WB SR-91 connector to SB SR-55
WB SR-91 Express Lanes between County Line and SR-55
WB Inside Lane on Santa Ana Canyon
DETOURS:
To Access WB SR-91:
Exit WB SR-91 Lakeview Avenue, turn right on Lakeview, turn left on La Palma Avenue, travel west and turn left on Tustin Avenue, continue to the WB SR-91 on-ramp.
To Access EB SR-91:
Travel east on Santa Ana Canyon Road, turn left on Imperial Highway and continue to the EB SR-91 on-ramp.
To Access SB SR-55:
Exit WB SR-91 Lakeview Avenue, turn left on Lakeview, turn right on Santa Ana Canyon Road, travel west and turn right on Nohl Ranch, turn left on Tustin Avenue, and turn left onto SB SR-55 on-ramp.
Segment 1: Lakeview to SR-55
Lakeview Avenue Bridge Construction
Progress at the Lakeview Avenue Bridge
Crews are continuing to pour concrete to form columns and build retaining walls and abutments to support the new Lakeview Avenue bridge. Keep an eye out for even more progress as we continue to construct this major structure!
Crews pouring concrete to form the columns of the new Lakeview Avenue bridge.
Crews forming the abutment for the new Lakeview Avenue bridge along the WB loop on-ramp at Lakeview.
Crews pouring concrete to form the footing for the new Lakeview Avenue bridge.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Crews are expected to continue daily work on the sound wall starting as early as 7 a.m. to 4 p.m. The new sound wall along the WB SR-91 on-ramp is anticipated to be complete by mid-2026.
Crews forming the concrete barrier for the sound wall along the WB 91 on-ramp at Lakeview.
Crews pouring concrete for the barrier of the sound wall along the WB 91 on-ramp at Lakeview.
Crews completing a section of the concrete pour for the barrier of the sound wall along the WB 91 on-ramp at Lakeview.
Along EB 91 On-Ramp at Lakeview
Crews have been forming and pouring the retaining wall along the EB SR-91 on-ramp. Crews are also making progress preparing the area for the foundation of the new bridge.
The retaining wall along the EB SR-91 on-ramp at Lakeview after concrete forms have been removed.
Crews placing structural backfill to support the foundation of the retaining wall along the EB SR-91 on-ramp at Lakeview.
Crews completing the structural backfill process to support the foundation of the retaining wall along the EB SR-91 on-ramp at Lakeview.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Segment 2: SR-55 to SR-57
Construction on Segment 2 of the SR-91 Improvement Project is expected to begin in mid-2026.
Segment 3: SR-57 Interchange
Construction on Segment 3 of the SR-91 Improvement Project is expected to begin in early 2026, bringing major upgrades to the SR-91/SR-57 interchange and surrounding areas to improve traffic flow, enhance safety, and support long-term mobility.
Nighttime lane closures on EB and WB SR-91 will occur regularly throughout construction. At least one lane will be open to traffic at all times, unless otherwise specified.
EB SR-91 Loop On-Ramp at Lakeview (Two-Year Closure):
The two-year closure started on July 7, 2025
For a full list of weekly closures and detours, and the most up-to-date project information, please click on the projectGoogle Mapbelow.
Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.
About the Project
91 Connect Business Program
The "91 Connect: Shop Local, Support Local" program supports businesses along the SR-91 Improvement Project corridor by promoting visibility and minimizing construction impacts through proactive outreach. Business spotlights on the project website, social media, and construction alerts, are all aimed to encourage the community to shop local and raise awareness of local businesses during construction. Click here to learn more.
Overview
The SR-91 (SR-57 to SR-55) Improvement Project will improve 6.6 miles of State Route 91 (SR-91) through Anaheim, Fullerton, Orange, Placentia and Yorba Linda. The project will improve mobility throughout the corridor, reduce weaving and merging between ramps, and improve on- and off-ramps. The project will reconstruct the La Palma Avenue, Kraemer Boulevard/Glassell Street, Tustin Avenue and Lakeview Avenue bridges and interchanges with standard lanes, shoulders and sidewalks in each direction. Visit our website for more information on segment and schedule details,octa.net/91improvements.