In observance of the holiday, there are no scheduled activities or closures for the SR-91 Improvement Project on Tuesday, Nov. 11. Thank you to all veterans for your service and sacrifice.
Canceled: Nighttime Westbound Full Directional Freeway Closure
The westbound (WB) SR-91 full directional freeway closure from Lakeview Avenue to SR-55/Tustin Avenue scheduled to begin on Saturday, Nov. 8 has been canceled. More information will be provided once the closure is rescheduled.
Lakeview Avenue Bridge Construction
Progress at the Lakeview Avenue Bridge
Crews have started building columns and retaining walls to support the new Lakeview Avenue bridge. This is exciting progress, as it marks the "above ground" portion of bridge construction after the conclusion of the first phase of pile driving for the foundation. Keep an eye out for even more progress as we continue to construct this major structure!
Crews completed backfilling in the center median and have started forming the columns for concrete pours.
Crews setting up the retaining wall concrete pours.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Crews are expected to continue daily work on the wall starting as early as 7 a.m. to 4 p.m. The new sound wall along the WB SR-91 on-ramp is anticipated to be complete by mid-2026.
Crews forming the concrete barrier for the sound wall along the WB 91 on-ramp at Lakeview.
Crews forming the roadway alongside the WB on-ramp in preparation for pouring additional concrete.
Crews preparing for concrete pour for the sound wall barrier along the WB on-ramp.
Along EB 91 On-Ramp at Lakeview
Crews have been forming and pouring the footings of the retaining wall along the eastbound (EB) 91 on-ramp. Crews are also making progress preparing the area for the foundation of the new bridge.
Crews preparing to form and pour the footings of the retaining wall.
Crews beginning the concrete pour along the EB 91 on-ramp.
Crews completing the concrete placement along the EB 91 on-ramp.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Segment 2: SR-55 to SR-57
Construction on Segment 2 of the SR-91 Improvement Project is expected to begin in early 2026.
Segment 3: SR-57 Interchange
Construction on Segment 3 of the SR-91 Improvement Project is expected to begin in early 2026. Stay tuned for updates.
Closures and Detours
Street Closures:
Ongoing and intermittently for the following two weeks, one lane of Lakeview Avenue between Santa Ana Canyon and the WB SR-91 off-ramp is anticipated to close on weekdays during daytime hours for electrical work.
Lakeview Avenue between Santa Ana Canyon and the WB SR-91 off-ramp for electrical work
As early as 10 p.m., Wednesday, Nov. 12 to 5 a.m., Thursday, Nov. 13
Freeway and Ramp Closures:
Nighttime lane closures on EB and WB SR-91 will occur regularly throughout construction. At least one lane will be open to traffic at all times, unless otherwise specified.
WB SR-91 Straight On-Ramp at Lakeview
As early as 9 p.m., Friday, Nov. 7 to 9 a.m., Saturday, Nov. 8
WB SR-91 Loop On-Ramp at Lakeview
As early as 9 p.m., Friday, Nov. 7 to 9 a.m., Saturday, Nov. 8
As early as 10 p.m., Wednesday, Nov. 12 to 5 a.m., Thursday, Nov. 13
EB SR-91 Straight On-Ramp at Lakeview
As early as 10 p.m., Wednesday, Nov. 12 to 5 a.m., Thursday, Nov. 13
EB SR-91 Loop On-Ramp at Lakeview (Two-Year Closure):
The two-year closure started on July 7, 2025
91 Express Lanes:
The following nighttime closures of the 91 Express Lanes will occur between SR-55/Tustin Avenue and the Orange County/Riverside County line.
WB 91 Express Lanes
As early as 9 p.m., Friday, Nov. 7 to 5 a.m., Saturday, Nov. 8
As early as 9 p.m., Friday, Nov. 14 to 5 a.m., Saturday, Nov. 15
EB 91 Express Lanes
As early as 11 p.m., Friday, Nov. 7 to 7 a.m., Saturday, Nov. 8
As early as 11 p.m., Friday, Nov. 14 to 7 a.m., Saturday, Nov. 15
For a full list of weekly closures and detours, and the most up-to-date project information, please click on the projectGoogle Mapbelow.
Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.
About the Project
91 Connect Business Program
The "91 Connect: Shop Local, Support Local" program supports businesses along the SR-91 Improvement Project corridor by promoting visibility and minimizing construction impacts through proactive outreach. Business spotlights on the project website, social media, and construction alerts, are all aimed to encourage the community to shop local and raise awareness of local businesses during construction. Click here to learn more.
Overview
The SR-91 (SR-57 to SR-55) Improvement Project will improve 6.6 miles of State Route 91 (SR-91) through Anaheim, Fullerton, Orange, Placentia and Yorba Linda. The project will improve mobility throughout the corridor, reduce weaving and merging between ramps, and improve on- and off-ramps. The project will reconstruct the La Palma Avenue, Glassell Street, Tustin Avenue and Lakeview Avenue bridges and interchanges with standard lanes, shoulders and sidewalks in each direction. Visit our website for more information on segment and schedule details,octa.net/91improvements.