For a full list of weekly closures and detours, and the most up-to-date project information, please click on the project Google Map below.
Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.
Segment 1: Lakeview to SR-55
Click the image above to view the Lakeview Avenue rendering on the project website.
Lakeview Avenue Bridge
Pile Driving at Lakeview Avenue
Crews completed the first portion of pile driving in the center median of the freeway and will continue during weekdays with the next phase of pile driving along westbound SR-91. Work at the remaining two locations is expected to conclude in early October. Crews may be on the worksite as early as 6 a.m. and are anticipated to perform pile driving activities from 7 a.m. to 4 p.m.
While pile driving is a critical step in the construction process, it may also be noisy and cause some vibration.
Excavation Activities
Crews are anticipated to excavate the area near the westbound (WB) loop on-ramp. Excavation activities involve removing soil and rocks from the area to prepare for the next phase of pile diving. This work is anticipated to occur nightly and begin as early as 10 p.m. to 5 a.m. on Monday, Sept. 22 and Tuesday, Sept. 23 (into Wednesday morning).
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Sound Wall Activities
Crews are expected to continue daily work on the wall as early as 7 a.m. to 4 p.m. The new sound wall is anticipated to be complete by mid-2026.
Crews demolishing the old sound wall to accommodate the new SB SR-55 direct on-ramp that will be built.
Crews pouring concrete to construct the stems, the main structural support of the new sound wall.
Crews pouring concrete to form stem walls to support the new sound wall further along the WB 91 on-ramp at Lakeview.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Upcoming Closures
Freeway and Ramp Closures:
Nighttime lane closures on eastbound (EB) and WB SR-91 will occur regularly throughout construction. At least one lane will be open to traffic at all times, unless otherwise specified.
WB Loop On-Ramp at Lakeview
As early as 9 p.m. Friday, Sept. 26 to 5 a.m. Saturday, Sept. 27
WB Straight On-Ramp at Lakeview
As early as 9 p.m. Friday, Sept. 26 to 5 a.m. Saturday, Sept. 27
EB 91 Loop On-Ramp at Lakeview (Two-Year Closure)
The two-year closure started on July 7, 2025.
About the Project
91 Connect Business Program
The "91 Connect: Shop Local, Support Local" program supports businesses along the SR-91 Improvement Project corridor by promoting visibility and minimizing construction impacts through proactive outreach. Business spotlights on the project website, social media, and construction alerts, are all aimed to encourage the community to shop local and raise awareness of local businesses during construction. Click here to learn more.
The SR-91 (SR-57 to SR-55) Improvement Project will improve 6.6 miles of State Route 91 (SR-91) through Anaheim, Fullerton, Orange, Placentia and Yorba Linda. The project will improve mobility throughout the corridor, reduce weaving and merging between ramps, and improve on- and off-ramps. The project will reconstruct the La Palma Avenue, Glassell Street, Tustin Avenue and Lakeview Avenue bridges and interchanges with standard lanes, shoulders and sidewalks in each direction. Visit our website for more information on segment and schedule details, octa.net/91improvements.