Tonight: 55-Hour Closure
Crews will perform construction activities on the westbound (WB) SR-91 off-ramp that will require continuous 55-hour closures starting as early as 9 p.m., Friday, July 10, through 4 a.m., Monday, July 13.
Closures:
WB SR-91 Lakeview Avenue off-ramp
Two outside lanes of WB SR-91
Detours:
Exit WB SR-91 at Imperial Highway off-ramp
Turn right onto Imperial Highway
Turn left onto La Palma Avenue and continue to access Lakeview Avenue
Exit WB SR-91 at Imperial Highway off-ramp
Turn left onto Imperial Highway
Turn right onto Santa Ana Canyon Road and continue to Lakeview Avenue
Segment 1: Lakeview to SR-55
Crews are expected to continue construction activities that will require a full Lakeview Avenue street closure between Santa Ana Canyon Road and the WB SR-91 off-ramp at Lakeview nightly, as early as Monday, July 13 through Friday, July 17 (into Saturday morning).
Intermittent nightly closures on Lakeview Avenue are expected to continue through July.
For a full list of weekly closures and detours, and the most up-to-date project information, please click on the project Google Map below.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Temporary Lakeview Configuration
A new temporary configuration on Lakeview Avenue is expected to occur in August 2026. More information will be provided.
Crews will continue electrical work and concrete pours at the Lakeview Avenue bridge intersection. Intermittent night work will continue as crews advance to the next phase of bridge construction. The new half of the bridge is expected to open later this summer. Stay tuned for additional information about upcoming lane configuration changes and the demolition of the remaining portions of the old bridge, which is also expected to occur later this summer.
Crews will continue night work activities during the week of July 13 at Lakeview Avenue.
Photos of the concrete deck pour, placing gravel to support the foundation and pouring concrete
on the new Lakeview Avenue bridge.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Crews are working on forming the barrier alongside the eastbound (EB) SR-91 off-ramp at Lakeview Avenue. Daily construction activities will start as early as 7 a.m. to 4 p.m.
Crews placing and grouting the blocks that form the top of the sound wall along the WB SR-91 on-ramp at Lakeview, placing structural backfill for the retaining wall along the EB SR-91 on-ramp at Lakeview and pouring concrete for the barrier along the EB SR-91 off-ramp at Lakeview.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Segment 2: SR-55 to SR-57
Construction on Segment 2 of the SR-91 Improvement Project is expected to begin in late 2026.
Segment 3: SR-57 Interchange
State College Boulevard Construction Activities
Crews will continue advancing roadway, drainage, bridge, and electrical improvements throughout the Segment 3 construction zone. Work will include excavation, shoring, temporary lighting installation, traffic control implementation, barrier work, and paving preparation, with activities occurring during both daytime and nighttime hours. State College Boulevard will remain open to traffic during most operations; however, intermittent overnight lane reductions, ramp closures, connector closures, and outside lane closures on SR-91 will be required to safely accommodate ongoing construction activities.
The SR-91 bridge over State College Boulevard is being widened to improve traffic flow and safety. Initial demolition of the existing bridge and re-striping work has been completed, and crews are now advancing foundation and bridge construction activities, including shoring and excavation. Motorists should continue to expect intermittent nighttime closures of State College Boulevard, on- and off-ramps, and outside SR-91 freeway lanes as work progresses.
For the latest construction information, traffic impacts, and closure updates, visit the project's Google Map and monitor future construction alerts.
Crews performed re-striping work on State College Boulevard to improve access to and from SR-91.
The images were taken during construction activities and do not reflect the completed traffic configuration.
Click here to view a full list of project closures.
Please note that construction schedules may be adjusted to accommodate traffic management needs associated with the FIFA World Cup, as well as inclement weather or unforeseen operational issues.
For a full list of weekly closures and detours, and the most up-to-date project information, visit our closure list please click on the projectGoogle Mapbelow.
Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.
About the Project
91 Connect Business Program
The "91 Connect: Shop Local, Support Local" program supports businesses along the SR-91 Improvement Project corridor by promoting visibility and minimizing construction impacts through proactive outreach. Business spotlights on the project website, social media, and construction alerts, are all aimed to encourage the community to shop local and raise awareness of local businesses during construction. Click here to learn more.
Overview
The SR-91 (SR-57 to SR-55) Improvement Project will improve 6.6 miles of State Route 91 (SR-91) through Anaheim, Fullerton, Orange, Placentia and Yorba Linda. The project will improve mobility throughout the corridor, reduce weaving and merging between ramps, and improve on- and off-ramps. The project will reconstruct the La Palma Avenue, Kraemer Boulevard/Glassell Street, Tustin Avenue and Lakeview Avenue bridges and interchanges with standard lanes, shoulders and sidewalks in each direction. Visit our website for more information on segment and schedule details,octa.net/91improvements.