June: National Safety Month
Speed limits are reduced in work zones to help protect everyone on the roadway. When traveling through active construction areas, slow down, stay alert, and follow posted speed limits. Taking a few extra moments to drive safely can help reduce the risk of crashes and keep traffic moving.
SR-91 Over State College Boulevard
Partial Demolition
WHAT:
The SR-91 bridge over State College Boulevard is being widened to improve traffic flow and safety. To complete this work, construction crews will close State College, on- and off-ramps and outside 91 freeway lanes to safely remove sections of the existing bridge. For detour information, please visit octa.net/91improvements
WHEN:
Anticipated nightly, 10 p.m. to 5 a.m., beginning as early as Monday, June 8 through Wednesday, June 10 into the following morning, and again Monday, June 15 to Wednesday, June 17 into the following morning.
WHERE:
WHAT TO EXPECT:
This work may be loud due to construction equipment, back up alarms, and concrete removal.
The schedule is subject to change due to inclement weather or unforeseen operational issues.
Segment 1: Lakeview to SR-55
Crews are anticipated to continue construction activities that will require a full Lakeview Avenue street closure between Santa Ana Canyon Road and the westbound (WB) SR-91 off-ramp at Lakeview nightly, as early as Friday, June 5 and Monday, June 8 through Friday, June 12 (into Saturday morning).
Intermittent nightly closures on Lakeview Avenue are expected to continue through mid-June.
For a full list of weekly closures and detours, and the most up-to-date project information, please click on the project Google Map below.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Temporary Lakeview Configuration
Motorists traveling both northbound (NB) and southbound (SB) on Lakeview Avenue will now use a new signalized intersection to access the newly realigned WB SR-91 straight on-ramp, and the WB SR-91 loop on-ramp at Lakeview Avenue has been permanently closed.
In this configuration, the eastern side of Lakeview Avenue is fully closed to pedestrians through August 2026. The western side is accessible to pedestrians.
Crews are hard at work. You may notice more traffic than usual. Please allow for extra time or utilize alternative routes.
Lakeview Avenue Bridge Construction
Intermittent night work will continue in the coming weeks as crews advance to the next phase of bridge construction. The new half of the bridge is expected to be open later this summer, stay tuned for additional information about lane configurations and demolition of the remaining portions of the old bridge.
Crews will continue night work activities during the week of June 8 at Lakeview Avenue.
Photos of the concrete deck pour on the new Lakeview Avenue bridge.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Crews continue work on a sound wall along the WB SR-91 on-ramp and a retaining wall along the EB SR-91 on-ramp. Daily construction activities will start as early as 7 a.m. to 4 p.m. The new wall is anticipated to be complete by mid-2026.
Crews placing and grouting the blocks that form the top of the sound wall along the WB SR-91 on-ramp and placing structural backfill for the retaining wall along the EB SR-91 on-ramp.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Segment 2: SR-55 to SR-57
Construction on Segment 2 of the SR-91 Improvement Project is expected to begin in late 2026.
Segment 3: SR-57 Interchange
State College Boulevard Construction Activities
Crews will continue striping activities and installation of temporary lighting and traffic control systems in the Segment 3 construction zone. Work will occur during both daytime and nighttime hours, with nighttime operations expected throughout much of the week. State College Boulevard will remain open to traffic; however, overnight lane reductions, ramp closures, and connector closures are required to safely complete this work.
The SR-91 bridge over State College Boulevard is being widened to improve traffic flow and safety. To complete this work, construction crews will close State College, on- and off-ramps and outside 91 freeway lanes to safely remove sections of the existing bridge. Overnight demolition and reconstruction activities are scheduled as early as Monday, June 8 through the morning of Thursday, June 11, and again Monday, June 15 through the morning of Thursday, June 18, from 10 p.m. to 5 a.m. This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
More information will be provided in upcoming construction alerts.
Crews continue concrete paving removal, clear and grubbing activities, and installing pedestrian access ramps within the project area.
Virtual Webinar
Did you miss our virtual webinar on May 26?
You can still catch up on the latest information about Segment 3 of the SR-91 Improvement Project by watching the webinar recording. During the presentation, the project team shared updates on upcoming construction activities, including plans to widen the SR-91 bridge over State College Boulevard, project benefits, construction schedules, and what nearby residents, businesses, and motorists can expect as work progresses.
As early as Friday, June 5, from 10 p.m. to 5 a.m., into the next morning
As early as Monday, June 8 through Friday, June 12, from 10 p.m. to 5 a.m. nightly, into the next morning
State College Boulevard:
As early as Monday, June 8 to Wednesday, June 10, from 10 p.m. to 5 a.m. nightly, into the next morning
Freeway and Ramp Closures:
Nighttime lane closures on EB and WB SR-91 and NB and SB SR-57 are anticipated to occur regularly throughout construction. At least one lane will be open to traffic at all times, unless otherwise specified.
EB SR-91 On-Ramp at Lakeview:
As early as Friday, June 5, from 10 p.m. to 5 a.m., into the next morning
As early as Monday, June 8 through Friday, June 12, from 10 p.m. to 5 a.m. nightly, into the next morning
WB SR-91 Off-Ramp at Lakeview:
As early as Friday, June 5, from 9 p.m. to 5 a.m., into the next morning
As early as Monday, June 8 through Friday, June 12, from 8 p.m. to 5 a.m. nightly, into the next morning
WB SR-91 Loop On-Ramp at Lakeview:
Permanently closed
EB SR-91 Loop On-Ramp at Lakeview (Two-Year Closure):
The two-year closure started on July 7, 2025
WB SR-91 Off-Ramp at State College Boulevard:
As early as Monday, June 8 to Wednesday, June 10, from 10 p.m. to 5 a.m. nightly, into the next morning
WB SR-91 On-Ramp at State College Boulevard:
As early as Monday, June 8 to Wednesday, June 10, from 10 p.m. to 5 a.m. nightly, into the next morning
EB SR-91 Off-Ramp at State College Boulevard:
As early as Monday, June 8 to Wednesday, June 10, from 10 p.m. to 5 a.m. nightly, into the next morning
EB SR-91 On-Ramp at State College Boulevard:
As early as Monday, June 8 to Wednesday, June 10, from 10 p.m. to 5 a.m. nightly, into the next morning
91 Express Lanes Closures:
The following nighttime closures of the 91 Express Lanes will occur between SR-55/Tustin Avenue and the Orange County/Riverside County line.
WB 91 Express Lanes:
As early as 9 p.m., Friday, June 5 to 5 a.m., Saturday, June 6
EB 91 Express Lanes:
As early as 11 p.m. Friday, June 5 to 7 a.m., Saturday, June 6
The schedule is subject to change due to inclement weather or unforeseen operational issues.
For a full list of weekly closures and detours, and the most up-to-date project information, please click on the projectGoogle Mapbelow.
Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.
About the Project
91 Connect Business Program
The "91 Connect: Shop Local, Support Local" program supports businesses along the SR-91 Improvement Project corridor by promoting visibility and minimizing construction impacts through proactive outreach. Business spotlights on the project website, social media, and construction alerts, are all aimed to encourage the community to shop local and raise awareness of local businesses during construction. Click here to learn more.
Overview
The SR-91 (SR-57 to SR-55) Improvement Project will improve 6.6 miles of State Route 91 (SR-91) through Anaheim, Fullerton, Orange, Placentia and Yorba Linda. The project will improve mobility throughout the corridor, reduce weaving and merging between ramps, and improve on- and off-ramps. The project will reconstruct the La Palma Avenue, Kraemer Boulevard/Glassell Street, Tustin Avenue and Lakeview Avenue bridges and interchanges with standard lanes, shoulders and sidewalks in each direction. Visit our website for more information on segment and schedule details,octa.net/91improvements.