August 1, 2022

REMINDER: I-5 FULL FREEWAY CLOSURES

CLOSURE REMINDER AUGUST 2-3


Crews are preparing for upcoming delivery and placement of pre-cast girders for the Los Alisos bridge, Aug. 2-3. This activity will require directional I-5 freeway closures nightly 

between El Toro Road and Alicia Parkway.


The precast girders will be placed as the primary support deck being constructed for the expansion of the Los Alisos bridge.



WHEN:

  • Tuesday, Aug. 2 and Wednesday, Aug. 3, 11 p.m. to 5 a.m.


WHAT TO EXPECT:

  • Southbound I-5 freeway closure, Aug. 2
  • Northbound I-5 freeway closure, Aug. 3
  • Nightly closure of Los Alisos Boulevard, (Carlota - Rockfield Blvd.)
  • Electronic message boards
  • Detour signage will be in place to assist motorists
Learn More

Southbound I-5 Closure

El Toro Rd. to Alicia Pkwy.

August 2, 2022

11 p.m. - 5 a.m.

Northbound I-5 Closure

Alicia Pkwy. to El Toro Rd. 

August 3, 2022

11 p.m. - 5 a.m.

The schedule is subject to change due to inclement weather or unforeseen operational issues.

TRAFFIC SIGNAL CONVERSION AT

AVENIDA DE LA CARLOTA

Crews will be installing a temporary three-way stop sign, replacing the existing traffic signal at the intersection of Avenida de la Carlota and Oakbrook Village. Relocation of the signal allows more room for crews to work on the retaining wall adjacent to the I-5 south. 


The traffic signal will be reinstalled once work is completed in early 2023. Please watch your speed in the construction area.  

PROJECT MILESTONE:

CROWN VALLEY PARKWAY OFF-RAMP

The newly widened off-ramp and auxiliary lane at southbound I-5 and Crown Valley Parkway has opened to motorists. This is a great milestone for the project to help alleviate congestion of traffic volume along this heavily traveled exit point. Take a drive and tell us what you think of the new ramp! 


VIEW THIS WEEK'S CLOSURES

ABOUT THE PROJECT
The project, which spans the cities of Mission Viejo, Lake Forest, Laguna Hills and Laguna Niguel, is expected to be completed in 2025.

OCTA and Caltrans are working together to improve freeway capacity and operations on a 6.5-mile stretch of I-5 from SR-73 to El Toro Road in south Orange County. This voter-approved $580-million project will: