As of April 10, 2026

Photo of a blue sky shows the Speed Limit 55 sign. Text on top reads "Slow For the Cone Zone. It's the Law! Slow Down in Work Zones." A traffic sign reads "Road Work Ahead".

📢 Don't Miss the Opportunity to

Join Us TOMORROW 📢

Image shows the location of Frontier Park where the community meeting will be held

OCTA's I-5 Improvement Project Community Outreach Team is hosting an in-person community meeting tomorrow, Saturday, April 11, at Frontier Park.


This meeting is being held as an opportunity for the community to learn about the project and ask questions.

IN-PERSON

Saturday, April 11

10 a.m. to 11 a.m.

Frontier Park

1400 Mitchell Ave, Tustin, CA 92780

SEE MAP ABOVE

To download the community meeting flyer, click below:

Thank You for Joining Our

Virtual Community Meeting

OCTA's I-5 Improvement Project Community Outreach Team hosted a virtual community meeting on Wednesday, April 8.


If you missed this meeting and would like to view its full recording, please click below:

Image shows the I-5 Project virtual community meeting recording available for viewing

Project Activities

Image shows concrete jersey barriers placed alongside an interstate highway

K-RAIL PLACEMENT, TEMPORARY RAMP CONSTRUCTION, & VEGETATION REMOVAL


WHAT:

Crews will place K-rail (concrete barriers that provide safety for both crews and motorists) as well as carry out temporary ramp construction and continue with vegetation removal along northbound (NB) and southbound (SB) I-5. Nighttime full ramp closures and freeway lane closures on NB and SB I-5 will be necessary starting as early as 10 p.m. Friday night, April 10, and continuing intermittently until 5 a.m. on Saturday morning, April 18. *


Additionally, crews continue with daytime activities including:

  • Vegetation Removal -- earthwork to safely prepare construction site for work.
  • Potholing -- small, controlled test holes to safely locate underground utilities (water, gas, electrical).
  • Temporary Road Surface -- placement of temporary asphalt.


At least one lane in each freeway direction will be open to traffic at all times, unless otherwise specified. See closures section below for more information. *


*This work may be loud and ongoing. Freeway lane closures will occur regularly throughout the duration of the project’s construction.

FREEWAY RAMP & LANE CLOSURES

For a full list of weekly closures and detours, and the most up-to-date project information, please click on the project Google Map below.

10 p.m. Friday night, April 10 to 
5 a.m. Saturday morning, April 11

  • NB I-5 Culver Drive on- and- off- ramps
  • NB I-5 Outside lane between Culver Drive and Jamboree Road
  • SB I-5 Tustin Ranch Road on-ramp

 

10 p.m. Wednesday night, April 15 to 
5 a.m. Thursday morning, April 16

  • NB I-5 Jamboree Road on- and- off- ramps
  • NB I-5 Two outside lanes between Culver Drive and Jamboree Road
  • SB I-5 Jamboree Road on-ramps
  • SB I-5 Two outside lanes between Jamboree Road and Culver Drive

10 p.m. Thursday night, April 16 to 
5 a.m. Friday morning, April 17

  • NB I-5 Culver Drive on-ramps
  • NB I-5 Tustin Ranch Road on-ramp
  • NB I-5 Two outside lanes between Culver Drive and Jamboree Road
  • SB I-5 Culver Drive on-ramps
  • SB I-5 Jamboree Road on-ramp
  • SB I-5 Two outside lanes between Jamboree Road and Culver Drive


10 p.m. Friday night, April 17 to

5 a.m. Saturday morning, April 18

  • NB I-5 Culver Drive on-ramps
  • NB I-5 Two outside lanes between Culver Drive and Jamboree Road
  • SB I-5 Jamboree Road on-ramps
  • SB I-5 Two outside lanes between Jamboree Road and Culver Drive

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues. 

Google Map

A clickable preview of the I-5 Improvement Project area on Google Maps. Click this image to view the interactive map on Google Maps.

Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.

""

Stay Connected

 

We invite you to sign up for project updates so you’ll be the first to know about upcoming construction activities, traffic changes, and community meetings and when we’ll be out in your community at local events - we hope you’ll stop by and say hello!



This screenshot outlines the I-5 Improvement website where constituents can sign up to receive Project Updates.
 

About the Project

Project Map

A horizontal map of the I-5 Improvement Project in Irvine and Tustin. Click the map to view it as a PDF.

Click to view a larger map

Click to view vertical map on a mobile device

A chart displays the Construction Schedule. Segment 1 is anticipated to be complete in late 2029. Segment 2 is anticipated to be complete in mid-2030. The schedule is subject to change.

For more information, view the Project Website and Fact Sheet:

" "
 
An illustration reads "Follow us on socials!" next to a cell phone on top of an orange background.

STAY CONNECTED

Facebook    X    Instagram    Web

i5Project405to55@octa.net

(888) 209-5550

octa.net/I-5Project

 
A footer image displays OCTA, Caltrans, US Department of Transportation and Building CA logos in a horizontal row..