Photo of a blue sky shows the Speed Limit 55 sign. Text on top reads "Slow For the Cone Zone. It's the Law! Slow Down in Work Zones." A traffic sign reads "Road Work Ahead".

有關此項目的更多信息,請聯繫 I-5 社區服务團隊,郵箱為 i5Project405to55@octa.net 或電話 888-209-5555,或查看 octa.net/i-5project.

 

이 프로젝트에 대한 자세한 내용은 I-5 Community Outreach Team에 이메일(i5Project405to55@octa.net) 또는 전화(888-209-5550)로 문의하시거나, octa.net/i-5project를방문해주시기바랍니다.

Project Activities

CONSTRUCTION ACTIVITIES UNDER

SR-261/I-5


WHAT:

Construction activities are expected to take place under the SR-261/I-5 bridge. Crews will carry out daytime pile driving activities for abutment work and nighttime cast-in-drilled-hole (CIDH) activities for bent work for the widening of I-5. *See below for more information on pile driving, CIDH, abutments, and bents.


Anticipated Pile Driving Daytime hours: as early as 7 a.m. to 4 p.m.

Anticipated CIDH Nighttime hours: as early as 10 p.m. to 5 a.m.


COMING SOON: Pile driving and CIDH activities and closures under the Jamboree Road/I-5 bridge and under the Peters Canyon Hiking and Riding Trail/I-5 bridge.


*This work may be loud and ongoing.

Bridge Sections

Image is of an infographic that explains what a bridge abutment is. A bridge abutment is a support structure at the end of a bridge that connects it to the earth and retains the earth.

Abutment: Support structure at each end of a bridge.

Image is of an infographic that demonstrates what a bridge bent is and how it is a support structure that supports the integrity of a bridge.

Bent: Support structure located beneath the middle portion of bridges.

Bridge Foundation Construction Methods

Image is of an infographic that demonstrates what the construction activity of pile driving looks like (hammering steel or concrete beams into the ground)

What is Pile Driving?

Pile driving is a commonly used method of constructing structure foundations.


To support the structure, a pre-fabricated steel or concrete beam or "pile" is hammered into the soil until it reaches a hard layer of earth beneath the structure foundation.


Activity is best carried out during the daytime due to:

  • Significant noise
  • More vibration
Image is of an infographic that demonstrates what cast-in-drilled-hole construction activity looks like

Cast-in-Drilled-Hole (CIDH)

Drilling of a hole into the ground first, using a steel casing for support and then filling the hole with concrete to form a pile.


Activity is best carried out during the nighttime due to:

  • Quieter
  • Minimal vibration
""

SIGN AND ELECTRICAL WORK &

ROADWAY EXCAVATION


WHAT:

Crews are anticipated to carry out roadway excavation and electrical work along northbound (NB) and southbound (SB) I-5. Nighttime full ramp closures and street and freeway lane closures (on NB and SB I-5) will be necessary starting as early as 10 p.m. Friday night, April 24, and continuing intermittently until 5 a.m. on Saturday morning, May 2. *


Additionally, crews continue with daytime activities including:

  • Vegetation removal -- Removal of shrubs and greenery as well as earthwork to safely prepare construction site for work.
  • Installation of construction area signs -- To notify the public of construction activity and guide safe travel.


At least one lane in each freeway and street direction will be open to traffic at all times, unless otherwise specified. See closures section below for more information. *


*This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues. Freeway and street lane closures will occur regularly throughout the duration of the project’s construction.

FREEWAY RAMP & LANE CLOSURES

For a full list of anticipated weekly closures and detours, and the most up-to-date project information, please click on the project Google Map below.

10 p.m. Friday night, April 24 to

5 a.m. Saturday morning, April 25

  • NB and SB I-5 lanes adjacent to the carpool (HOV) lanes between Tustin Ranch Road and SR-55

 

10 p.m. Monday night, April 27 to 
5 a.m. Tuesday morning, April 28

  • SB I-5 lane adjacent to the HOV lane between SR-55 and Tustin Ranch Road


10 p.m. Tuesday night, April 28 to

5 a.m. Wednesday morning, April 29

  • (Surface street) EB Tustin Ranch Road outside lane at I-5
  • NB I-5 Jamboree Road on- and- off- ramps
  • NB I-5 Two outside lanes between Culver Drive and Jamboree Road
  • SB I-5 Jamboree Road on-ramps
  • SB I-5 Two outside lanes between Jamboree Road and Culver Drive


10 p.m. Wednesday night, April 29 to 
5 a.m. Thursday morning, April 30

  • (Surface Street) EB Tustin Ranch Road outside lane at I-5
  • NB I-5 Tustin Ranch Road on- and- off- ramps
  • NB and SB I-5 lanes adjacent to the HOV lanes between Tustin Ranch Road and SR-55


10 p.m. Thursday night, April 30 to

5 a.m. Friday morning, May 1

  • (Surface Street) EB Tustin Ranch Road outside lane at I-5
  • NB I-5 Tustin Ranch Road on- and- off- ramps
  • NB and SB I-5 lanes adjacent to the HOV lanes between Tustin Ranch Road and SR-55


10 p.m. Friday night, May 1 to

5 a.m. Saturday morning, May 2

  • (Surface Street) EB Tustin Ranch Road outside lane at I-5
  • NB I-5 Tustin Ranch Road on- and- off- ramps
  • NB and SB I-5 lanes adjacent to the HOV lanes between Tustin Ranch Road and SR-55


This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues. 

Google Map

A clickable preview of the I-5 Improvement Project area on Google Maps. Click this image to view the interactive map on Google Maps.

Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.

""

Stay Connected

 

We invite you to sign up for project updates so you’ll be the first to know about upcoming construction activities, traffic changes, and community meetings and when we’ll be out in your community at local events - we hope you’ll stop by and say hello!



This screenshot outlines the I-5 Improvement website where constituents can sign up to receive Project Updates.
 

About the Project

Project Map

A horizontal map of the I-5 Improvement Project in Irvine and Tustin. Click the map to view it as a PDF.

Click to view a larger map

Click to view vertical map on a mobile device

A chart displays the Construction Schedule. Segment 1 is anticipated to be complete in late 2029. Segment 2 is anticipated to be complete in mid-2030. The schedule is subject to change.

For more information, view the Project Website and Fact Sheet:

" "
 
An illustration reads "Follow us on socials!" next to a cell phone on top of an orange background.

STAY CONNECTED

Facebook    X    Instagram    Web

i5Project405to55@octa.net

(888) 209-5550

octa.net/I-5Project

 
A footer image displays OCTA, Caltrans, US Department of Transportation and Building CA logos in a horizontal row..