SR-57 NB Improvement Project and OCTA logo with the SR-57 NB Freeway in the background.

As of April 27, 2026

For more information about this project, please contact the Community Outreach Team, by calling (800) 440-0457, by email at 57NBproject@octa.net or visit octa.net/57NBproject.


Para obtener más información sobre este proyecto, comuníquese con el Equipo de Alcance Comunitario llamando al (800) 440-0457, enviando un correo electrónico a 57NBproject@octa.net o visite octa.net/57NBproject.

Project Activities

Please be advised that his work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

BRIDGE DEMOLITIONS

Santa Ana River Bridge

Crews will demolish a portion of the Santa Ana River bridge over the Santa Ana River in the upcoming weeks.


This work will require the two outside lanes on the right-hand side.


Northbound (NB) SR-57 will be closed between the NB SR-57 on-ramp to Orangewood Ave. and the SR-57 off-ramp to Katella Ave.


The NB SR-57 closure is anticipated as early as 11 p.m., Friday, May 1, to 5 a.m. Friday, May 8.

RAMP & LANE CLOSURES

*On game nights for the Los Angeles Angels and Anaheim Ducks, closures will start at 11 p.m.


NB Orangewood Avenue Loop On-Ramp

Intermittent closures, from 10 p.m. to 5 a.m., Thursday night, April 30 to Saturday morning, May 2


NB Orangewood Avenue Straight On-Ramp

Intermittent closures, from 10 p.m. to 5 a.m., Monday night, April 27 to Wednesday morning, April 29 and again on Thursday night, April 30 to Saturday morning, May 2


NB Katella Avenue Off-Ramp

Intermittent closures, from 10 p.m. to 5 a.m., Thursday night, April 30 to Saturday morning, May 2


NB SR-57 lane closures between Chapman Avenue and Katella Avenue

Intermittent lane closures, from 10 p.m. to 5 a.m., Monday night, April 27 to Wednesday morning, April 29


*At least one lane will be open to traffic at all times, unless otherwise specified.


EB/WB Orangewood Avenue at SR-57

Road closures, from 10 p.m. to 6 a.m., starting Monday night, April 27 to Tuesday morning, April 28

PILE INSTALLATION ACTIVITIES

Orangewood Avenue

Crews will continue installing piles at Orangewood Avenue adjacent to the northbound SR-57.


Ongoing from 6:30 a.m. to 4 p.m. for approximately one week.


Crews may mobilize as early as 6 a.m.


Santa Ana River

Crews will continue installing piles at the Santa Ana River adjacent to the northbound SR-57.


Ongoing from 6:30 a.m. to 4 p.m. and may continue for several weeks.


Access at the Santa Ana River Trail will be maintained at all times. Flaggers will assist cyclists and pedestrians, as needed.



The SR-57 Community Outreach Team will provide updates in future alerts.


Crews may mobilize as early as 6 a.m.

Speed Limit/Safety Reminder: Please look out for posted speed limit and traffic control signs. Slow down within construction work zones, for the safety of motorists and crews.

Interactive Map

For a full list of weekly closures and detours, and the most up-to-date project information, please click on the project Google Map below.

Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.

Stay Connected!

We invite you to sign up for project updates so you’ll be the first to know about upcoming construction activities, traffic changes, and community meetings and when we’ll be out in your community at local events we hope you’ll stop by and say hello!

About the Project