As of June 12, 2026

NATIONAL SAFETY MONTH


Speed matters. Slow down. Save lives.


As traffic lane patterns change on the freeway, please stay alert and follow the implemented 55 miles-per-hour speed limit throughout construction zones. Together, we can help ensure motorists and construction crews get home safely.

June is National Safety Month and the I-5 Improvement Project team encourages everyone to follow speed limits and help ensure construction crews and motorists get home safely.
Photo of a blue sky shows the Speed Limit 55 sign. Text on top reads "Slow For the Cone Zone. It's the Law! Slow Down in Work Zones." A traffic sign reads "Road Work Ahead".

有關此項目的更多信息,請聯繫 I-5 社區服务團隊,郵箱為 i5Project405to55@octa.net 或電話 888-209-5555,或查看 octa.net/i-5project.

 

이 프로젝트에 대한 자세한 내용은 I-5 Community Outreach Team에 이메일(i5Project405to55@octa.net) 또는 전화(888-209-5550)로 문의하시거나, octa.net/i-5project를방문해주시기바랍니다.

Segment 1 (I-405 to Yale Avenue)

Project Activities

ONGOING WORK

Crews continue with temporary striping on northbound (NB) and southbound (SB) I-5. Nighttime full ramp closures and freeway shoulder and lane closures will be necessary as early as 2:30 a.m. Saturday, June 13, and continuing intermittently until 5 a.m. on Saturday, June 20. See closures below for more information.


The City of Irvine continues to carry out utility activities and require the nighttime closure of the left side shoulder on NB Sand Canyon Avenue at the I-5 bridge starting as early as 9 p.m. Tuesday night, June 16, through 5 a.m. Wednesday morning, June 17.


Anticipated Work Hours

Daytime Hours: As early as 7 a.m. to 4 p.m.

Nighttime Hours: As early as 9 p.m. to 5 a.m.

*This work may be loud and ongoing. The schedule is subject to change due to inclement weather or unforeseen operational issues.


*Freeway and street lane closures will occur regularly throughout the duration of the project's construction. At least one lane will be open to traffic at all times, unless otherwise specified. See closure section below for more information.

Segment 2 (Yale Avenue to SR-55)

Project Activities

ONGOING WORK

A multi-lane highway with construction cones set out to shift vehicles towards a new traffic pattern

TRAFFIC SHIFTS ON RAMPS AND ROADWAY


Nighttime construction activities are ongoing at the Tustin Ranch Road, Jamboree Road, and Culver Drive on- and off-ramps. Temporary asphalt concrete placement has been completed at the ramps and crews continue placing temporary striping and concrete barriers to reduce freeway lanes as traffic is being shifted toward the center of the roadway. This work facilitates the ongoing traffic shifts onto the temporary ramps allowing demolition and reconstruction of existing ramps to begin.


Anticipated Schedule

Temporary Asphalt Concrete Placement: Completed.

Traffic Shift Activity: Ongoing through June.


Once shifted, traffic will remain on the temporary paved ramps through spring 2027 before being switched to the permanent, newly reconstructed ramps.


Reduced freeway lanes will also allow for crews to work on the outside portions of NB and SB I-5 through the remainder of 2026 for construction of retaining walls and bridge widening.


Anticipated Work Hours

Daytime Hours: As early as 7 a.m. to 4 p.m.

Nighttime Hours: As early as 10 p.m. to 5 a.m.

Large construction machinery staged off to the shoulder of a multi-lane freeway meant for the purpose of pile driving activities

BRIDGES AT

JAMBOREE ROAD/I-5 AND SR-261/1-5


Construction activities continue under the bridges at Jamboree Road/I-5 and SR-261/I-5 for bridge widening, including cast-in-drilled-hole (CIDH) and pile driving to widen structures as part of project improvements.


Please note that pile driving activities may be loud at times and are scheduled during daytime hours.


Anticipated Schedule

SR-261/I-5: Ongoing through late June.

Jamboree Road/I-5: Ongoing through early July.


Anticipated Work Hours

Daytime Hours: As early as 7 a.m. to 4 p.m.

Nighttime Hours: As early as 10 p.m. to 5 a.m.


Closures

24/7 Long-Term Closure: Crews have installed concrete barriers and closed the lanes nearest to the median on Jamboree Road at the I-5 bridge in both directions. At least one lane in each direction will remain open to traffic at all times unless otherwise noted.


Lane closures and intermittent nighttime full closures on eastbound (EB) and westbound (WB) Jamboree Road at I-5 will continue through late 2026 to support I-5 widening work.

STRIPING, K-RAIL, AND

SIGN REMOVAL ACTIVITIES


Crews continue with striping and concrete barrier (K-rail) activities as well as the removal of freeway signs along NB and SB I-5. Nighttime full ramp closures and street and freeway lane closures are necessary starting as early as 10 p.m. Saturday night, June 13, and continuing intermittently until 9 a.m. on Saturday, June 20.

COMING SOON

NB & SB SR-261 FULL CLOSURES

AT THE I-5 BRIDGE


Nighttime construction activities are anticipated for demolition of the outer portions of I-5 at SR-261. This work will require full closures of NB and SB SR-261. Please note, crews will first close the NB side of SR-261 to complete bridge work. Upon completion, crews will shift activities to the SB side of SR-261 to complete work on the other side of the bridge.


Please check the Google Map below for additional closure and detour information.


Anticipated Schedule

June 22 through early July 2026


Anticipated Work Hours

Daytime Hours: As early as 7 a.m. to 4 p.m.

Nighttime Hours: As early as 10 p.m. to 5 a.m.

CONSTRUCTION ACTIVITIES AT

I-5/PETERS CANYON HIKING & RIDING TRAIL


Daytime construction activities are expected to take place at the I-5/Peters Canyon Hiking and Riding Trail Bridge for CIDH work.


Anticipated Schedule

As soon as mid-to-late-June through late 2026


Anticipated Work Hours

Daytime Hours: As early as 7 a.m. to 4 p.m.

Nighttime Hours: As early as 10 p.m. to 5 a.m.


Closures

Nighttime freeway lane and ramp closures will occur for restriping and concrete barrier placement. Lanes will be reduced and traffic will be shifted towards the center of the freeway while crews work on the outside bridge portions of NB and SB I-5 through the remainder of 2026.


Intermittent full closures of the Peters Canyon Hiking and Riding Trail at I-5 may occur through late 2026 for moving equipment in the construction area.

A photo of retaining wall construction activities along the northbound I-5 freeway at Culver Drive

RETAINING WALL CONSTRUCTION


Construction activities are expected to take place along the NB I-5 Culver Drive on-ramp area for the construction of a new retaining wall.


Anticipated Schedule

As soon as late June through late 2026 (daytime and nighttime shifts).


Anticipated Work Hours

Daytime Hours: As early as 7 a.m. to 4 p.m.

Nighttime Hours: As early as 10 p.m. to 5 a.m.


Closures

Daytime work will occur behind concrete barriers, while nighttime work will require freeway lane closures and intermittent closures of ramps including the NB I-5 Culver Drive on-ramp.

*This work may be loud and ongoing. The schedule is subject to change due to inclement weather or unforeseen operational issues.


*Freeway and street lane closures will occur regularly throughout the duration of the project's construction. At least one lane will be open to traffic at all times, unless otherwise specified. See closure section below for more information.

STREET, FREEWAY, AND FULL RAMP CLOSURES

For a full list of anticipated weekly closures and detours, and the most up-to-date project information, please click on the project Google Map below.

Segment 1 Closures (I-405 to Yale Avenue)

9 p.m. Tuesday night, June 16 to 5 a.m. Wednesday morning, June 17

  • SB I-5 Connector to SB SR-133
  • SB I-5 Jeffrey Road on- and- off- ramps
  • SB I-5 lanes closure between Jeffrey Road and SR-133
  • (Surface Street) NB Sand Canyon Avenue left-side shoulder at the I-5 bridge

9 p.m. Wednesday night, June 17 to

5 a.m. Thursday morning, June 18

  • SB I-5 lanes closure between SR-133 and Alton Parkway off-ramp
  • SB I-5 Sand Canyon Road on- and- off- ramps (2:30 a.m. to 5:00 a.m.)
  • SB I-5 Jeffrey Road on- and- off- ramps
  • SB I-5 lanes closure between Jeffrey Road and SR-133

Segment 2 Closures (Yale Avenue to SR-55)

10 p.m. Saturday night, June 13 to

8 a.m. Sunday morning, June 14

  • (Surface Street) EB Jamboree Road full street closure at I-5
  • (Surface Street) WB Jamboree Road three inside lanes closed between NB I-5 on-ramp and SB I-5 off-ramp


10 p.m. Tuesday night, June 16 to

5 a.m. Wednesday morning, June 17

  • (Surface Streets) WB and EB Jamboree Road full street closures at I-5
  • NB I-5 outside lane closure between Jeffrey Road and the NB I-5 Culver Drive on-ramp
  • NB I-5 Jamboree Road on- and- off- ramps

10 p.m. Wednesday night, June 17 to

5 a.m. Thursday morning, June 18

  • (Surface Street) WB and EB Culver Drive full street closures at I-5
  • (Surface Street) WB and EB Jamboree Road between the SB I-5 on-ramp and the NB I-5 off-ramp (at least one lane will remain open at all times)
  • NB I-5 Culver Drive on- and- off- ramps
  • NB I-5 outside lanes closure between Jeffrey Road and Jamboree Road
  • NB I-5 Jamboree Road on-ramps
  • SB I-5 outside lane closure between Jamboree Road and Culver Drive
  • SB I-5 outside lanes closed between Tustin Ranch Road and Jamboree Road


10 p.m. Friday night, June 19 to

5 a.m. Saturday morning, June 20

  • (Surface Street) EB Culver Drive full street closures at I-5
  • NB I-5 outside lane closure between Jeffrey Road and the NB I-5 Culver Drive on-ramp
  • SB I-5 outside lanes closure between Jamboree Road and Jeffrey Road


Google Map

A clickable preview of the I-5 Improvement Project area on Google Maps. Click this image to view the interactive map on Google Maps.

Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.

""

Stay Connected

 

We invite you to sign up for project updates so you’ll be the first to know about upcoming construction activities, traffic changes, and community meetings and when we’ll be out in your community at local events - we hope you’ll stop by and say hello!



This screenshot outlines the I-5 Improvement website where constituents can sign up to receive Project Updates.
 

About the Project

Project Map

A horizontal map of the I-5 Improvement Project in Irvine and Tustin. Click the map to view it as a PDF.

Click to view a larger map

Click to view vertical map on a mobile device

A chart displays the Construction Schedule. Segment 1 is anticipated to be complete in late 2029. Segment 2 is anticipated to be complete in mid-2030. The schedule is subject to change.

For more information, view the Project Website and Fact Sheet:

" "
 
An illustration reads "Follow us on socials!" next to a cell phone on top of an orange background.

STAY CONNECTED

Facebook    X    Instagram    Web

i5Project405to55@octa.net

(888) 209-5550

octa.net/I-5Project

 
A footer image displays OCTA, Caltrans, US Department of Transportation and Building CA logos in a horizontal row..