ONGOING WORK - BRIDGES AT
JAMBOREE ROAD/I-5 AND SR-261/1-5
Construction activities continue under the bridges at Jamboree Road/I-5 and SR-261/I-5 for bridge widening, including cast-in-drilled-hole (CIDH) and pile driving to widen structures as part of overall project improvements.
Anticipated Schedule:
Jamboree Road/I-5: Ongoing through early July during daytime and nighttime shifts.
SR-261/I-5: Ongoing through late June during daytime and nighttime shifts.
Daytime Work: As early as 7 a.m. to 4 p.m.
Nighttime Work: As early as 10 p.m. to 5 a.m.
Closures
24/7 Long-Term Closure: Crews have installed concrete barriers and closed the lanes nearest to the median on Jamboree Road at the I-5 bridge in both directions. At least one lane in each direction will remain open to traffic at all times unless otherwise noted. *
Lane closures and intermittent nighttime full closures on eastbound (EB) and westbound (WB) Jamboree Road at I-5 will continue through late 2026 to support I-5 widening work.
|