As of May 8, 2026

Photo of a blue sky shows the Speed Limit 55 sign. Text on top reads "Slow For the Cone Zone. It's the Law! Slow Down in Work Zones." A traffic sign reads "Road Work Ahead".

有關此項目的更多信息,請聯繫 I-5 社區服务團隊,郵箱為 i5Project405to55@octa.net 或電話 888-209-5555,或查看 octa.net/i-5project.

 

이 프로젝트에 대한 자세한 내용은 I-5 Community Outreach Team에 이메일(i5Project405to55@octa.net) 또는 전화(888-209-5550)로 문의하시거나, octa.net/i-5project를방문해주시기바랍니다.

Segment 2 - Project Activities

*This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues. Freeway and street lane closures will occur regularly throughout the duration of the project’s construction.

BRIDGE CONSTRUCTION ACTIVITIES UNDER JAMBOREE ROAD/I-5


Construction activities are expected to take place under the Jamboree Road/I-5 Bridge for bridge widening. Bridge widening activities include cast-in-drilled-hole (CIDH), pile driving and falsework.


Anticipated Work Schedule at Jamboree/ I-5

CIDH and Pile Driving: As early as mid-May through early July.

Falsework and Other Bridge Widening Activities: Early July through late 2026.



Anticipated Work Hours

Daytime Work: As early as 7 a.m. to 4 p.m.

Nighttime Work: As early as 10 p.m. to 5 a.m.


Closures

Daytime Long-Term Lane Closures: As early as Wednesday, May 13, crews will place concrete barriers in the lanes closest to the median and close them off in both directions of Jamboree Road at the I-5 bridge. At least one lane in each direction will be open to traffic at all times, unless otherwise specified.

  • Lane closures for eastbound (EB) and westbound (WB) Jamboree Road at I-5 will remain in place until late 2026 to support additional I-5 widening work.

Intermittent Nighttime Full Street Closures: EB and WB Jamboree Road at I-5.



For more closures and detours information, see the maps below, the Closures section, and the Google Map.

Image displays a map that depicts the Eastbound Jamboree Road closure in red and the appropriate detour routes in green depicted by arrows showing the approved direction of traffic
Image displays a map that depicts the Westbound Jamboree Road closure in red and its appropriate detour routes depicted in green arrows showing the approved direction of traffic
Crews excavating abutments at Jamboree bridge
Installing temporary ramp metering at NB Jamboree on-ramp

Photos of crews excavating abutments at Jamboree bridge (left) and installing temporary ramp metering at NB Jamboree on-ramp (right)

ONGOING - CONSTRUCTION ACTIVITIES UNDER SR-261/I-5


Construction activities are expected to take place under the SR-261/I-5 Bridge for bridge widening. Bridge widening activities include cast-in-drilled-hole (CIDH), pile driving and falsework.


Anticipated Work Schedule

CIDH and Pile Driving: Ongoing through late June.


Anticipated Work Hours

Daytime Work: As early as 7 a.m. to 4 p.m.

Nighttime Work: As early as 10 p.m. to 5 a.m.

COMING SOON - CONSTRUCTION ACTIVITIES UNDER PETERS CANYON HIKING AND RIDING TRAIL/I-5


Construction activities are expected to take place under the Peters Canyon Hiking and Riding Trail/I-5 Bridge for bridge widening. Bridge widening activities include cast-in-drilled-hole (CIDH) and falsework.


Anticipated Work Schedule

CIDH Dates: As early as late May throughout late June.


Anticipated Work Hours

Daytime Work: As early as 7 a.m. to 4 p.m.

Nighttime Work: As early as 10 p.m. to 5 a.m.


Check back for any related closures.

CIDH drilling at SR-261
Constructing the CIDH rebar cage

Photos of crews CIDH drilling at SR-261 (left) and constructing the CIDH rebar cage (right)

COMING SOON - TEMPORARY ASPHALT CONCRETE PAVING


Nighttime construction activities are expected to occur at different on- and- off- ramps for the placement of temporary asphalt concrete. Traffic will be shifted onto the temporary pavement to allow for the demolition and reconstruction of existing ramps. *


Anticipated Dates: As early as mid-May. *

Anticipated Nighttime Work Hours: As early as 10 p.m. to 5 a.m. *


*Check back for schedule updates as well as updates for ramp locations, closures, and detour information.

Image is of construction machinery removing the top surface layer of vegetation alongside a freeway

VEGETATION REMOVAL, ROADWAY EXCAVATION, STRIPING AND PAVING


Crews continue with vegetation removal, roadway excavation, and temporary striping and paving on northbound (NB) and southbound (SB) I-5, NB and SB SR-261, and on surface streets. Nighttime full ramp closures and street and freeway lane closures will be necessary starting as early as 10 p.m. Friday night, May 8 and continuing intermittently until 5 a.m. on Saturday, May 16. *


At least one lane in each freeway and street direction will be open to traffic at all times, unless otherwise specified. See closures section below for more information. *

STREET LANE, FREEWAY, AND RAMP CLOSURES

For a full list of anticipated weekly closures and detours, and the most up-to-date project information, please click on the project Google Map below.

10 p.m. Friday night, May 8 to

5 a.m. Saturday morning, May 9

  • NB I-5 outside lane between Jeffrey Road and Culver Drive
  • NB I-5 Culver Drive off-ramp


10 p.m. Monday night, May 11 to

5 a.m. Tuesday morning, May 12

  • NB I-5 outside lane between Culver Drive and Jamboree Road
  • NB I-5 Jamboree Road off-ramp
  • NB and SB I-5 Jamboree Road on-ramps
  • NB and SB SR-261 outside lanes between the Walnut Avenue on-ramp and El Camino Real bridge


10 p.m. Tuesday night, May 12 to

5 a.m. Wednesday morning, May 13

  • NB I-5 Culver Drive on- and- off- ramps

10 p.m. Wednesday night, May 13 to 
5 a.m. Thursday morning, May 14

  • (Surface Street) EB and WB Jamboree Road Full Street Closure at I-5
  • NB I-5 Culver Drive off- ramps


10 p.m. Thursday night, May 14 to

5 a.m. Friday morning, May 15

  • NB I-5 Tustin Ranch Road off-ramp



10 p.m. Friday night, May 15 to

5 a.m. Saturday morning, May 16

  • NB I-5 outside lane between Jamboree Road and Tustin Ranch Road
  • NB I-5 Tustin Ranch Road off-ramp


Google Map

A clickable preview of the I-5 Improvement Project area on Google Maps. Click this image to view the interactive map on Google Maps.

Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.

Starting NEXT WEEK!

I-5 Improvement Project - Segment 1

Between I-405 and Yale Avenue

Segment 1 - Project Activities

Crews are expected to begin preliminary construction activities such as installing striping, and concrete barriers, and begin vegetation removal on NB and SB I-5 as early as 7 a.m. Monday, May 11 through early June. *


Anticipated Daytime Work Hours: As early as 7 a.m. to 4 p.m.

Anticipated Nighttime Work Hours: As early as

10 p.m. to 5 a.m.


*Nighttime lane closures on NB and SB I-5 will occur regularly throughout construction. At least one lane will be open to traffic at all times, unless otherwise specified.


*This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

""

Stay Connected

 

We invite you to sign up for project updates so you’ll be the first to know about upcoming construction activities, traffic changes, and community meetings and when we’ll be out in your community at local events - we hope you’ll stop by and say hello!



This screenshot outlines the I-5 Improvement website where constituents can sign up to receive Project Updates.
 

About the Project

Project Map

A horizontal map of the I-5 Improvement Project in Irvine and Tustin. Click the map to view it as a PDF.

Click to view a larger map

Click to view vertical map on a mobile device

A chart displays the Construction Schedule. Segment 1 is anticipated to be complete in late 2029. Segment 2 is anticipated to be complete in mid-2030. The schedule is subject to change.

For more information, view the Project Website and Fact Sheet:

" "
 
An illustration reads "Follow us on socials!" next to a cell phone on top of an orange background.

STAY CONNECTED

Facebook    X    Instagram    Web

i5Project405to55@octa.net

(888) 209-5550

octa.net/I-5Project

 
A footer image displays OCTA, Caltrans, US Department of Transportation and Building CA logos in a horizontal row..