As of July 10, 2026

有關此項目的更多信息,請聯繫 I-5 社區服务團隊,郵箱為 i5Project405to55@octa.net 或電話 888-209-5555,或查看 octa.net/i-5project.

 

이 프로젝트에 대한 자세한 내용은 I-5 Community Outreach Team에 이메일(i5Project405to55@octa.net) 또는 전화(888-209-5550)로 문의하시거나, octa.net/i-5project를방문해주시기바랍니다.

Click on this image to view construction activities on the project interactive map.
Image is of a clipboard with a traffic cone on it to encourage people to click on the link next to it to view a detailed closure list

To view and print a detailed list of closures and detours, CLICK HERE!

Segment 2 (Yale Avenue to SR-55)

Project Activities

ONGOING WORK

BRIDGE DEMOLITION & PILE DRIVING/CIDH ACTIVITIES AT CULVER DRIVE/I-5 BRIDGE

Image shows available detour routes for Westbound Culver Drive full closures
Image shows available detour routes for Eastbound Culver Drive full closures

Nighttime construction activities and closures are starting for the demolition of the outer portions of I-5 at Culver Drive. This work will require full closures of westbound (WB) and eastbound (EB) Culver. Please note, crews will first close one direction of Culver to complete the bridge work before moving to the opposite direction.

 

Additionally, construction activities are coming soon at the Culver/I-5 bridge, including cast-in-drilled-hole (CIDH) and pile driving to widen structures as a part of project improvements. Intermittent nighttime full closures and lane closures on EB and WB Culver at I-5 will occur during the pile driving activity to support I-5 widening work.

 

24/7 Long-Term Closure: Crews will install concrete barriers and close inside lanes on Culver at the I-5 bridge in both directions for a 24/7 long-term closure to conduct CIDH activities, to be scheduled this fall. At least one lane in each direction will remain open at all times, unless otherwise noted.  Check back for the 24/7 long-term closure implementation date. Once implemented, the long-term closure will remain in place until mid-2027.

 

Please note: To account for daytime traffic impacts, demolition activities are scheduled during nighttime hours. To account for nighttime noise impacts, pile driving and CIDH activities are scheduled during daytime hours. Both demolition and pile driving activities may be loud at times.

 

For more information on these closures and associated detours, please click on the Google Map and/or view the detour maps below.

 

Anticipated Schedule

Demolition: Monday, July 13 through Friday, July 17.

Pile Driving: Mid-July through fall 2026.

CIDH: fall 2026.

 

Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 10 p.m. to 5 a.m.

RETAINING WALL AND SOUND WALL CONSTRUCTION


Retaining wall (RW) and sound wall (SW) construction activities are ongoing and expected to continue along northbound (NB) and southbound (SB) I-5.


Anticipated Schedule

  • RW along SB I-5 between Culver and Georgia: Ongoing through late 2026.
  • SW along NB I-5 Culver and Yale Avenue: Ongoing through late 2026.
  • RW and SW along SB I-5 between Butterfly and Culver: Ongoing through late 2026.
  • RW along NB I-5 Culver on-ramp: Late July through late 2026.


Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 10 p.m. to 5 a.m.


Closures

Daytime work is anticipated to occur behind concrete barriers while nighttime work requires freeway lane closures and intermittent closures of NB and SB I-5 Culver on- and- off- ramps.

I-5 PETERS CANYON HIKING/RIDING TRAIL


Daytime construction activities are ongoing at the I-5/Peters Canyon Hiking and Riding Trail Bridge for CIDH work.


Anticipated Schedule

Ongoing through late 2026.


Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 10 p.m. to 5 a.m.


Intermittent full closures of the Peters Canyon Hiking and Riding Trail at I-5 may occur through late 2026 for moving equipment in the construction area.

TRAFFIC SHIFTS ON RAMPS AND ROADWAY


Crews continue shifting traffic toward the center of I-5 as well as on the Tustin Ranch Road, Jamboree Road, and Culver Drive on- and- off- ramps.


Anticipated Schedule

Traffic Shift Activity: Ongoing through mid-to-late-July.


Once shifted, traffic will remain on the temporary paved ramps through Spring 2027 before being switched to the permanent, newly reconstructed ramps.


Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 10 p.m. to 5 p.m.

BRIDGE AT SR-261/I-5 - PILE DRIVING


Construction activities continue under the bridge at SR-261/I-5 including pile driving to widen structures as a part of project improvements.


Please note, pile driving activities may be loud at times and are scheduled during daytime hours.


Anticipated Schedule

SR-261/I-5: Ongoing through late July.


Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 10 p.m. to 5 a.m.


24/7 Long-Term Closure: Crews have installed concrete barriers and closed the lanes nearest the median on Jamboree Road at the I-5 bridge in both directions. At least one lane will remain open at all times, unless otherwise noted.


Lane closures and intermittent nighttime full closures are expected through late 2026 to support I-5 widening work.

COMING SOON: I-5 OUTREACH TEAM IN YOUR COMMUNITY

Image shows a person interacting with the I-5 Outreach Team at a pop-up booth
 
Image depicts the I-5 Outreach Team hosting a pop-up booth at a community event

OTHER ACTIVITIES


Crews continue with general highway construction, bridge and electrical work, striping activities, and equipment transport on NB and SB I-5 and on Jamboree Road and Culver Drive. Nighttime full ramp closures and street and freeway lane closures are necessary starting as early as 1 a.m. Friday, July 10 and continuing intermittently until 5 a.m. on Saturday, July 18.


City of Irvine Long-Term Closure

Please note: Ongoing through October, the City of Irvine and Irvine Ranch Water District (IRWD) will continue water relocation activities on Culver near the I-5 bridge. This work requires WB Culver under the bridge to be reduced to one lane. Work and lane closures are expected Monday through Friday, from 9 a.m. to 3 p.m. Please contact the City of Irvine or IRWD for more information.

RESUMING SOON

BRIDGE DEMOLITION AND FULL ROAD CLOSURES AT JAMBOREE ROAD/I-5 BRIDGE


Nighttime construction activities and closures will resume soon for the demolition of the outer portions of I-5 at Jamboree Road. This work requires intermittent full road closures of WB and EB Jamboree. Please note that crews will switch between EB and WB directions of Jamboree intermittently to conduct the work and implement closures.


Anticipated Schedule

EB and WB Jamboree: Mid-to-Late July.


Anticipated Work Hours

Daytime: As early as 6 a.m. to 4 p.m.

Nighttime: As early as 10 p.m. to 5 a.m.

*This work may be loud and ongoing. The schedule is subject to change due to inclement weather or unforeseen operational issues.


*Freeway and street lane closures will occur regularly throughout the duration of the project's construction. At least one lane will be open to traffic at all times, unless otherwise specified. See closure section above for more information.

Segment 1 (I-405 to Yale Avenue)

Project Activities

ONGOING WORK

Crews continue with concrete barrier (K-rail) activities, temporary striping, lighting placement, vegetation removal, and ramp activities on NB and SB I-5 as well as on SR-133. Nighttime full ramp closures and street and freeway lane closures will be necessary as early as 9 p.m. Monday, July 13 and continuing intermittently until 5 a.m. on Saturday, July 18. See closures section below for more information.


The City of Irvine continues to carry out underground utility activities. Closures of the median and inside lanes along Sand Canyon Avenue at I-5 are necessary starting as early as 9 p.m. Monday, July 13 through 4 a.m. Friday, July 17.


Anticipated Work Hours

Daytime: As early as 7 a.m. to 4 p.m.

Nighttime: As early as 9 p.m. to 5 a.m.

*This work may be loud and ongoing. The schedule is subject to change due to inclement weather or unforeseen operational issues.


*Freeway and street lane closures will occur regularly throughout the duration of the project's construction. At least one lane will be open to traffic at all times, unless otherwise specified. See closure section above for more information.

Google Map

A clickable preview of the I-5 Improvement Project area on Google Maps. Click this image to view the interactive map on Google Maps.

Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.

""

Stay Connected

 

We invite you to sign up for project updates so you’ll be the first to know about upcoming construction activities, traffic changes, and community meetings and when we’ll be out in your community at local events - we hope you’ll stop by and say hello!



This screenshot outlines the I-5 Improvement website where constituents can sign up to receive Project Updates.
 

About the Project

Project Map

A horizontal map of the I-5 Improvement Project in Irvine and Tustin. Click the map to view it as a PDF.

Click to view a larger map

Click to view vertical map on a mobile device

A chart displays the Construction Schedule. Segment 1 is anticipated to be complete in late 2029. Segment 2 is anticipated to be complete in mid-2030. The schedule is subject to change.

For more information, view the Project Website and Fact Sheet:

" "
 
An illustration reads "Follow us on socials!" next to a cell phone on top of an orange background.

STAY CONNECTED

Facebook    X    Instagram    Web

i5Project405to55@octa.net

(888) 209-5550

octa.net/I-5Project

 
A footer image displays OCTA, Caltrans, US Department of Transportation and Building CA logos in a horizontal row..