Daytime construction activities, and some nighttime activities, are ongoing behind k-rail (concrete barriers) at various bridge locations along I-5. Activities include abutment work, girder installation, removal of temporary support structures, concrete pours for new bridge deck areas, barrier wall work, and roadway reconstruction to widen bridge structures as a part of project improvements.
For more information on closures and associated detours, please view the Google Interactive Map, or plan your route using the Waze navigation app.
Anticipated Schedule
El Modena Tustin Channel/I-5 Bridge
-
Abutment Work: Ongoing through late December.
-
Girder Installation: Tentatively Tuesday, Dec. 1.
(Nighttime activity with partial mainline and ramp closures.)
Peters Canyon Hiking and Riding Trail/I-5 Bridge
-
Bridge Foundation and Abutment Work: Week of Nov. 9 through spring 2027.
-
Wall Demolition/Partial Pedestrian & Bike Lane Closure: Tentatively Monday, Nov. 16. (Weather permitting. Partial access of the bike and pedestrian lanes will be maintained.)
-
Temporary Support Structures Installation/Girder Installation: Tentatively late-November through mid-January 2027.
Nighttime activity with full road closures; check back for more details.
Jamboree/I-5 Bridge
-
Rebar Work/New Deck Area Concrete Pours: Week of Nov. 30.
-
Barrier Wall Work: Mid-December through January 2027.
One nighttime full road closure is expected in January; check back for more details.
-
Roadway Reconstruction: Early 2027 through September 2027.
SR-261/I-5 Bridge
- Temporary Support Structures Removal: Friday, Nov. 13 and Monday, Nov. 16.
(Weather permitting).
-
New Deck Area Concrete Pours: Week of Nov. 30.
-
Barrier Wall Work: Mid-December through January 2027.
One nighttime full road closure is expected in January; check back for more details.
Culver Drive/I-5
-
Long-Term Lane Closures: Tentatively Monday, Nov. 30 (weather permitting).
Lane closest to the median in both directions of Culver at I-5 for cast-in-drill-hole (CIDH) work. Check back for more details.
- NIGHTTIME ACTIVITIES:
-
CIDH Activities: Tentatively week of Dec. 7 through Friday, Dec. 18.
Nighttime full lane closures will be required. Check back for more details.
-
Bent, Girder, Rebar and Deck Work: December 2026 through January 2027.
Anticipated Work Hours
Daytime: As early as 6 a.m. to 4 p.m.
Nighttime: As early as 10 p.m. to 5 a.m.
Nighttime freeway lane and ramp closures will occur intermittently. At least one lane in each direction will remain open at all times, unless otherwise noted.
|