Daytime construction activities, and some nighttime activities, are ongoing behind k-rail (concrete barriers) at various bridge locations along I-5. Activities include abutment work, girder installation, removal of temporary support structures, concrete pours for new bridge deck areas, barrier wall work, and roadway reconstruction to widen bridge structures as a part of project improvements.
For more information on closures and associated detours, please view the Google Interactive Map, or plan your route using the Waze navigation app.
Anticipated Schedule
El Modena Tustin Channel/I-5 Bridge
-
Abutment Work: Ongoing through late December.
-
Girder Installation: Tentatively, mid-December.
(Nighttime activity with partial mainline and ramp closures.)
Peters Canyon Hiking and Riding Trail/I-5 Bridge
-
Bridge Foundation, Abutment and Wall Work: Ongoing through spring 2027.
-
Temporary Support Structures Installation/Girder Installation: Tentatively, late 2026 through winter 2027.
Nighttime activity with full road closures; check back for more details.
Jamboree/I-5 Bridge
-
Rebar Work: Ongoing through Week of Dec. 7.
-
New Deck Concrete Pours: Tuesday, Dec. 8 and Thursday, Dec. 10
-
Barrier Wall Work: Winter 2027.
One nighttime full road closure is expected in February; check back for more details.
-
Roadway Reconstruction: Early 2027 through September 2027.
SR-261/I-5 Bridge
-
New Deck Concrete Pours: Tuesday, Dec. 1 and Thursday, Dec. 3.
-
Temporary Support Structures Removal: Winter 2027.
Two nights of full road closures are expected in February; check back for more details.
Anticipated Work Hours
Daytime: As early as 6 a.m. to 4 p.m.
Nighttime: As early as 10 p.m. to 5 a.m.
Nighttime freeway lane and ramp closures will occur intermittently. At least one lane in each direction will remain open at all times, unless otherwise noted.
|