1st Avenue | 2nd Street - 5th Street
Crews have completed underground work and continue to move forward on concrete paving, sidewalks, and streetscaping. The current traffic pattern will continue for the next couple of weeks before traffic will shift and allow crews to work on a new area of the road. One lane will continue to be open each direction. Future work will include the additional pedestrian signing and decorative fencing. You’ll see this work in the final phases. The project is on track to be completed by this fall.