APRIL 10, 2023

UPCOMING CLOSURES, KNOW BEFORE YOU GO

Did you know... 

you can view weekly closures on the I-5 South County Improvements map on octa.org/i5southcounty?

Click on the link below to learn more.

VIEW CLOSURE MAP

ONLINE COMMUNITY MEETING

Join the I-5 South County Improvements team for an online community meeting Wednesday, April 12 at 5:30 p.m. as we share project progress from our hard-working crews and upcoming closure information. The meeting will take place on Zoom and will be recorded for later viewing.

REGISTER NOW

I-5 EL TORO ROAD LANE REDUCTIONS AND

RAMP CLOSURES

Crews will be conducting drainage and paving work at I-5 and El Toro Road requiring

eastbound and westbound nightly lane reductions from Rockfield Boulevard to Avenida De La Carlota, 9 p.m. to 5 a.m., Monday, April 10 to Friday, April 14. In addition, northbound and southbound I-5 ramps will also be closed nightly. Detours will be in place.


WHEN:

  • Eastbound El Toro Rd., Monday, April 10, 9 p.m. to 5 a.m.
  • Westbound El Toro Rd., nightly, 9 p.m. to 5 a.m. Monday, April 10 to Friday, April 14



WHAT TO EXPECT:

  • Nightly lane reductions on El Toro Rd. between Rockfield Blvd. to Ave. De La Carlota
  • Nightly ramp closures from 11 p.m. to 5 a.m., northbound off-ramp and loop on-ramp, and the southbound loop and direct on-ramp
  • Signage will be in place to assist motorists with detours


The schedule is subject to change due to inclement weather or unforeseen operational issues.

PILE DRIVING SCHEDULED

SOUTHBOUND I-5 ADJACENT TO

 AVENIDA DE LA CARLOTA

Crews are performing pile driving work along southbound I-5 adjacent to Avenida De La Carlota as of Friday, April 7. Crews will be constructing the new concrete barrier and retaining wall along southbound I-5 at the Los Alisos bridge. 



WHEN:

  • Pile driving began on Friday, April 7, and will continue for up to three weeks.
  • Work is scheduled weekdays, 6 a.m. to 6 p.m.


WHAT TO EXPECT:

  • Construction noise
  • A total of 95 piles are needed at the location


The schedule is subject to change due to inclement weather or unforeseen operational issues.

AVERY PARKWAY CLOSURE

Avery Parkway at I-5 is scheduled to be closed nightly, beginning April 17 for up to three nights, so crews can safely and efficiently deliver precast concrete girders. Nighttime southbound I-5 Avery Pkwy. off-and on-ramps will also be closed as part of this activity, along with mainline lane reductions.


The girders are a structural component of the I-5 improvements at Avery Pkwy. and are roughly 82' long and weigh almost 68,000 lbs. Because of the size and weight, a specialized crane will be used to place the girders.


WHEN:

• Nightly, 10 p.m. to 6 a.m., Monday, April 17, for up to three nights.


WHAT TO EXPECT:

• Nighttime full closure of Avery Pkwy. under I-5 with no through access

• Nightly southbound I-5 Avery Pkwy. off-and on-ramp closures

• Nightly lane reductions on southbound I-5 at Avery Pkwy.


The schedule is subject to change due to inclement weather or unforeseen operational issues. 

DISTRACTED DRIVING AWARENESS

VIEW THIS WEEK'S CLOSURES

ABOUT THE PROJECT
The project, which spans the cities of Mission Viejo, Lake Forest, Laguna Hills and Laguna Niguel, is expected to be completed in 2025.

OCTA and Caltrans are working together to improve freeway capacity and operations on a 6.5-mile stretch of I-5 from SR-73 to El Toro Road in south Orange County. This voter-approved $580-million project will: