JANUARY 16, 2023

UPCOMING CLOSURES, KNOW BEFORE YOU GO

Did you know... you can view weekly closures on the I-5 South County Improvements map on octa.org/i5southcounty?

Click on the link below to learn more.

VIEW GOOGLE MAP

RAMP CLOSURES AND LANE REDUCTIONS

OSO PARKWAY AND LA PAZ ROAD


Crews will be conducting paving operations requiring nightly ramp closures at northbound I-5 La Paz Road off-ramp and southbound I-5 Oso Parkway on-ramp. Lane reductions will also take place on La Paz Rd. between Muirlands Blvd. and Cabot Rd. Please follow detour signage.



WHEN:

  • Nightly, Monday, Jan. 16 through Friday, Jan. 20, 10 p.m. to 5 a.m.


WHAT TO EXPECT:

  • Nightly ramp closures at northbound I-5 La Paz Rd. off-ramp
  • Nightly ramp closures at southbound I-5 Oso Pkwy. on-ramps
  • Nightly lane reductions at La Paz Rd. from Muirlands Blvd. to Cabot Rd.
  • Detour signage will be in place to assist motorists


The schedule is subject to change due to inclement weather or unforeseen operational issues.

LANE REDUCTIONS FOR BRIDGE WORK

EL TORO ROAD

Watch for nightly lane reductions on El Toro Rd. as crews continue bridge work this week at El Toro Rd. between Rockfield Blvd. and Ave. De La Carlota. Please follow detour signage.


WHEN:

  • Nightly, Monday, Jan. 16, through Friday, Jan. 20, 9 p.m. to 5 a.m.


WHAT TO EXPECT:

  • Westbound and eastbound lane reductions on El Toro Rd. between Rockfield Blvd. and Ave. De La Carlota
  • Detour signage will be in place to assist motorists


The schedule is subject to change due to inclement weather or unforeseen operational issues.

NIGHTLY LANE REDUCTIONS AT

AVERY PARKWAY

Crews will continue bridge work requiring nightly lane reductions this week at Avery Pkwy. between Camino Capistrano and Marguerite Pkwy. Please follow detour signage.


WHEN:

  • Nightly, Monday, Jan. 16, through Friday, Jan. 20, 9 p.m. to 5 a.m.



WHAT TO EXPECT:

  • Westbound and eastbound lane reductions on Avery Pkwy. between Camino Capistrano and Marguerite Pkwy.
  • Detour signage will be in place to assist motorists


The schedule is subject to change due to inclement weather or unforeseen operational issues.

VIEW THIS WEEK'S CLOSURES

ABOUT THE PROJECT
The project, which spans the cities of Mission Viejo, Lake Forest, Laguna Hills and Laguna Niguel, is expected to be completed in 2025.

OCTA and Caltrans are working together to improve freeway capacity and operations on a 6.5-mile stretch of I-5 from SR-73 to El Toro Road in south Orange County. This voter-approved $580-million project will: