WEEK OF JUNE 6, 2022

MILESTONE AT AVERY PARKWAY

IMG_8940.JPEG


IMG_8989.JPEG

Project Milestone!

Crews completed placement of 24 girders for the Avery Parkway bridge construction over a two-night operation last week. The girders are a structural component of the I-5 widening at Avery Parkway and are roughly 82' long and weigh almost 68,000 lbs. Because of the size and weight, a specialized crane was used to place the girders.

ALICIA PARKWAY RAMP CLOSURES

Alicia Southeast.JPG

Nightly ramp closures will occur this week at I-5 and Alicia Parkway, for bridge and roadway excavation work. Please look for detour signage and slow your speed in the construction area. 


WHEN:

  • 11 p.m. to 5 a.m., nightly, Monday, June 6 through Friday, June 10


WHAT TO EXPECT: 

  • Northbound Alicia Pkwy. loop on-ramp nightly closures
  • Northbound Alicia Pkwy. direct on-ramp nightly closures
  • Southbound direct on-ramp nightly closures
  • Signage will be in place to assist motorists with detours


View Closure List

The schedule is subject to change due to inclement weather or unforeseen operational issues.

VIEW THIS WEEK'S CLOSURES
The schedule is subject to change due to inclement weather or unforeseen operational issues.
ABOUT THE PROJECT
The project, which spans the cities of Mission Viejo, Lake Forest, Laguna Hills and Laguna Niguel, is expected to be completed in 2025.

OCTA and Caltrans are working together to improve freeway capacity and operations on a 6.5-mile stretch of I-5 from SR-73 to El Toro Road in south Orange County. This voter-approved $580-million project will: