WEEK OF MAY 31, 2022

AVERY PARKWAY GIRDER DELIVERY

IMG_8015 _2_.JPEG

Avery Parkway at I-5 is scheduled to be closed Wednesday, June 1, so crews can safely and efficiently deliver precast concrete girders. Nightly lane reductions will be in place on Avery Pkwy. Thursday, June 2 and Friday, June 3. The girders are a structural component of the I-5 widening at Avery Parkway and are roughly 82' long and weigh almost 68,000 lbs. Because of the size and weight, a specialized crane will be used to place the girders.



WHEN:

  • Nightly, 10 p.m. to 5 a.m., starting as early as Wednesday, June 1 for up to three nights.


WHAT TO EXPECT:

  • Nighttime full closure of Avery Pkwy. under I-5 with no through access on Wednesday, June 1.
  • Nightly lane reductions on Avery Pkwy. at I-5 on June 2-3.
  • Nightly lane reductions on northbound I-5 at Avery Pkwy. on June 1-3.
  • Signage will be in place to assist motorists with detours.


The schedule is subject to change due to inclement weather or unforeseen operational issues.

Learn More

UPDATED: ALICIA PARKWAY PILE DRIVING

Pile Driving Graphics_square 2021.jpg

Crews continue performing pile driving work along northbound I-5 near Alicia Parkway off-ramp through mid-June. Pile driving is necessary for the foundation of the retaining wall. 



WHEN:

  • Daily through through mid-June as planned
  • Crews will work weekdays 7 a.m. to 5 p.m.
  • Saturday work may occur, beginning June 4, 7 a.m. to 5 p.m.


WHAT TO EXPECT:

  • Construction noise is expected.
  • A total of 200 piles are needed at this location.


The schedule is subject to change due to inclement weather or unforeseen operational issues.

UPCOMING RAMP CLOSURES

Ramp Closure.png

Nightly ramp closures will occur this week at I-5 and Oso ParkwayLa Paz Road, Alicia Parkway, and El Toro Road on-and off-ramps. 


Please watch for detour signage and reduce your speed in the construction area.

View Closure List

The schedule is subject to change due to inclement weather or unforeseen operational issues.

CONGRATULATIONS GRADUATES

Graduates 2022.jpg

Congratulations to the graduating class of 2022 from Saddleback Valley Unified School District, Capistrano Valley Unified School District and Saddleback Community College! Your futures are very bright and we wish you continued success! 

VIEW THIS WEEK'S CLOSURES
The schedule is subject to change due to inclement weather or unforeseen operational issues.
ABOUT THE PROJECT
The project, which spans the cities of Mission Viejo, Lake Forest, Laguna Hills and Laguna Niguel, is expected to be completed in 2025.

OCTA and Caltrans are working together to improve freeway capacity and operations on a 6.5-mile stretch of I-5 from SR-73 to El Toro Road in south Orange County. This voter-approved $580-million project will: