Week of Oct. 2, 2023

CONTINUING RAMP CLOSURE

Extended Closure of the I-5 Northbound On-ramp from El Toro Road

WHAT:


Crews continue to reconstruct the I-5 northbound loop on-ramp from El Toro Road, requiring an extended closure of the ramp.


Plan for additional travel time through the area.


WHEN:


I-5 NB El Toro Road Loop On-ramp Closed

  • 11 p.m. Friday, Sept. 29 - 5 a.m., Monday, Oct. 9



Safe and direct detours will be in place.



The schedule is subject to change due to inclement weather or unforeseen operational issues.

DETOUR FOR RAMP CLOSURE

PILE DRIVING THIS WEEK

Pile driving to occur near I-5 northbound straight on-ramp from Crown Valley Parkway

WHAT:


Crews are nearing completion on sound walls along the I-5 northbound near Crown Valley Parkway and the Kaleidoscope shopping center. The final round of pile driving to place the sound walls will begin this week. This work may occur at all hours for three weeks.


Prepare for noise and vibration in the area.


WHEN:


Pile driving near Crown Valley Parkway

  • Oct. 4 - Oct. 25



The schedule is subject to change due to inclement weather or unforeseen operational issues.

UPCOMING CLOSURES THIS WEEK

Be Aware and Prepare


Oct. 2-Oct. 8, expect overnight freeway lane reductions and closures, ramp closures and street closures.


Plan for additional travel time through the area. 

WHAT TO EXPECT: I-5 LANE REDUCTIONS/ClOSURES

NORTHBOUND I-5


Nightly lane reductions/closures from:

  • SR-73 to Crown Valley Parkway starting as early as 8 p.m.
  • Oso Parkway to El Toro Road as early as 8 p.m.


SOUTHBOUND I-5


Nightly lane reductions/closures from:

  • El Toro Road to La Paz Road Parkway starting as early as 8 p.m.
  • Oso Parkway to SR-73 starting as early as 8 p.m.


WHAT TO EXPECT: I-5 RAMP CLOSURES

RAMP CLOSURES


Nightly ramp closures at:

  • Avery Parkway, Crown Valley Parkway, Oso Parkway, Alicia Parkway and El Toro Road starting as early as 10 p.m.


Safe and direct detours will be in place.



The schedule is subject to change due to inclement weather or unforeseen operational issues.

CLOSURES TO KNOW

Before You Hit The Road


You can view weekly closures on the I-5 South County Improvements map on octa.net/i5southcounty.


Click on the link below to learn more.

VIEW CLOSURE MAP

VIEW THIS WEEK'S CLOSURES

ABOUT THE PROJECT

The project, which spans the cities of Mission Viejo, Lake Forest, Laguna Hills and Laguna Niguel, is expected to be completed in 2025.


OCTA and Caltrans are working together to improve freeway capacity and operations on a 6.5-mile stretch of I-5 from SR-73 to El Toro Road in south Orange County. This voter-approved $580-million project will: