WHAT:
Crews are nearing completion on retaining walls along northbound I-5 near Crown Valley Parkway and the Kaleidoscope shopping center.
The final round of pile driving for the retaining walls began last week.
This work is anticipated to continue the day for several weeks.
Prepare for noise and vibration in the area.
WHEN:
Pile driving expected to continue through Wednesday, Oct. 25.
Note: This activity may require daytime closures of the Crown Valley Parkway straight on-ramp to NB I-5.
The potential closures are scheduled for:
- 9 a.m. to 3 p.m. Thursday, Oct. 12, and Friday, Oct. 13.
The schedule is subject to change due to inclement weather or unforeseen operational issues.
|