West Cliff Update

January 2024

Construction Update


920 West Cliff

- The wall has reached its top elevation.

- This week, the team will be backfilling the back of the wall and placing an 8-ton rip rap at the front and sides of the wall.


932 West Cliff

- The wall is expected to reach its top elevation this week.

- Granite crews will pour concrete for the last section of the concrete wall on Friday, 1/19/24.


1016 West Cliff

- This week, Granite will backfill the adjacent sea cave that collapsed due to the recent storm.

- They will also continue to build formwork for the retaining wall.


1030 West Cliff

- The design team is discussing and reviewing possible wall designs for this site.


Reminder: barricades are there for your safety! Please never move or go past barricades and stay out of the construction zone.

Community Conversations: 50-Year Vision for West Cliff


Join us to learn more about the 50-Year Vision for West Cliff!

On January 30 from 5:30-7pm, we'll hold a virtual meeting to dive into the data gathered from your input and share your feedback on the insights we've gained so far!


Join Zoom Meeting

https://us06web.zoom.us/j/86795185521

Learn more about the project that is underway!