Construction Update
Johnson-Morristown STP 2919(1)
& 2920(1)


[VT 15 Resurfacing and VT 15A Resurfacing Projects]

DATE: Friday, September 16, 2022


TRAFFIC IMPACT AND DURATION: Monday, September 19 through Friday, September 23, between 6 a.m. and 6 p.m., there will be minimal traffic impacts with minor delays on VT Route 15 (VT 15). Flaggers will be in place to assist motorists.


CONSTRUCTION ACTIVITIES: Crews will be installing remaining signage throughout the project limits and working on punch list items. 


LOCATION:

Johnson-Morristown STP 2919(1): Beginning on VT 15 in the Town of Johnson, just east of Collins Hill Road and extending easterly for 9.489 miles through the Town of Hyde Park and stopping at mile point 4.182 in the Town of Morristown. Also, beginning on VT 100 (Historic VT 100) in the Town of Morristown near Professional Drive and extending northerly 0.413 miles to the intersection with VT 15.

 

Morristown STP 2920(1): Beginning on VT 15A in Morristown 0.36 miles east of the intersection with VT 12 and extending easterly to the intersection with VT 15.


PROJECTED COMPLETION: Fall 2022

Johnson-Morristown STP 2919(1) Fact Sheet
Morristown STP 2920(1) Fact Sheet
For more information:
Public Information Consultant: Delia Makhetha
Project Hotline: 603-263-8881
Facebook  Twitter  Instagram  
To learn more about VTrans Construction Projects, visit our projects website.