Construction Update
Johnson-Morristown STP 2919(1)
& 2920(1)


[VT 15 Resurfacing and VT 15A Resurfacing Projects]
DATE: Friday, July 29, 2022

TRAFFIC IMPACT AND DURATION: Monday, August 1 through Friday, August 5, between 6 a.m. and 6 p.m., there will be lane closures with alternating one-way traffic on VT Route 15 in Johnson and Hyde Park. Flaggers will be in place to assist motorists. 

Motorists are advised to drive with caution through the work zone. 

CONSTRUCTION ACTIVITIES: Crews will begin paving the final wearing course, starting in Johnson and working towards the Hyde Park Roundabout. 

LOCATION:
Johnson-Morristown STP 2919(1): Beginning on VT 15 in the Town of Johnson, just east of Collins Hill Road and extending easterly for 9.489 miles through the Town of Hyde Park and stopping at mile point 4.182 in the Town of Morristown. Also, beginning on VT 100 (Historic VT 100) in the Town of Morristown near Professional Drive and extending northerly 0.413 miles to the intersection with VT 15.
 
Morristown STP 2920(1): Beginning on VT 15A in Morristown 0.36 miles east of the intersection with VT 12 and extending easterly to the intersection with VT 15.

PROJECTED COMPLETION: Fall 2022
For more information:
Public Information Consultant: Delia Makhetha
Project Hotline: 603-263-8881