GCEP Project Update

Hello Alexia,

Thank you for opting in to recieve regular email updates on the Greater Cambridge Energy Project (GCEP). Please see below for the latest updates on construction activities in your area.

Trench Excavation and Duct Bank Installation


As the Project continues trench excavation in several Cambridge locations, additional crews follow behind to install underground duct bank. The trench is then backfilled and temporarily restored in sections.


The typical process includes:

  • Sawcut existing pavement or concrete
  • Excavate trench and remove soils, area is covered daily with steel road plates.
  • Install duct bank into excavated trench
  • Backfill and temporarily restore trench

Duct bank is a group of tubes, known as conduit, that house and organize electrical cables. Once the duct bank is completely installed on GCEP, the electric cables can be pulled through each underground tube (conduit).


Trench excavation and duct bank installation are ongoing on Linskey Way, Third Street, and Ames Street in Cambridge.

Construction Update

July 14 - July 25

City of Cambridge


Approved construction hours in Cambridge


  • Monday to Friday from 7 a.m. to 4 p.m.
  • Occasional activities may be performed beyond these hours or on weekends based on approval from local officials.


Ongoing activities


  • Broadway:
  • As part of the Kendall Common redevelopment and GCEP, traffic and pedestrian changes were implemented June 6 on Broadway between Galileo Way and Third and Main Street. Learn more.
  • Crews are installing transmission line conduit within the new substation site, off the roadway at 121 Broadway. This activity is ocurring Monday through Saturday.


  • Third Street:
  • Excavation activities are ongoing off the roadway at the corner of Third Street and Broadway (Volpe parcel) to install underground duct bank. The trench excavation and duct bank installation has transitioned onto Third Street progressing towards Linskey Way. Work at this location will continue throughout the summer months. 
  • A temporary sidewalk closure will be in place on the west side of Third Street between Potter Street and Broadway. Please utilize pedestrian crosswalks at Broadway and Kendall Street
  • Linskey Way:
  • Both underground vaults have been set on Linskey Way. 
  • Excavation activities are ongoing, progressing ontoThird Street. A crew will follow behind to install duct bank, backfill, and temporarily restore the roadway. Work to excavate trench and install duct bank will be ongoing throughout the summer months. 
  • Ames Street: 
  • Excavation activities are ongoing to support the installation of underground duct bank between Memorial Drive and Amherst Street. This will necessitate a closure on Ames Street between Memorial Drive and Amherst Street. Motorists should follow posted signage.
  • Memorial Drive: 
  • Crews will be performing soil boring activities at various locations, starting near the Ames Street intersection and progressing west toward River Street. Crews anticipate completing borings at multiple locations per day.
  • Lane restrictions will be necessary. "No parking" signs will be clearly displayed in advance of these activities.

Traffic Configurations


  • Construction activities will generally be done utilizing lane restrictions or alternating lane traffic patterns. If detours are necessary, clear signage will be posted to direct motorists and cyclists. Please continue to check the project website for updates and postings of traffic plans.
  • During daytime construction activities, Linskey Way may be closed at Third Street. During these times, all vehicles will enter and exit Linskey Way via Binney Street and Second Street. Alternating traffic patterns may be necessary on Linskey Way. This traffic pattern is needed while crews transition from Linskey onto Third Street.
  • Southbound traffic on Ames Street will be detoured at Main Street, to Wadsworth Street. Northbound traffic on Ames Street will remain open between Amherst Street and Main Street. This traffic pattern will continue during daytime work hours. Additionally, starting on June 2, there will be a permanent closure of Ames Street (northbound and southbound) between Memorial Drive and Amherst Street. Motorists should follow posted detour signage.

City of Somerville / City of Boston


There is no construction planned in Somerville or Boston at this time.

Please continue to check this newsletter for updates.

Click the image below to view our

Interactive Project Map!

Visit the GCEP Website to learn more


Have a question about the Project or its approved routes? Please reply to this email with any questions or to setup a meeting.

Keeping You Informed

Eversource is committed to being a good neighbor and keeping you informed of Project progress.