Celebrating Earth Day the Right Way: Volunteers Keeping our Riverbanks Clean!


In celebration of Earth Day on April 22, Eversource is proud to partner with the Charles River Watershed Association (CRWA) to help clean and restore riverbanks in the community. Last year, our volunteers made a meaningful impact — removing more than 50 bags of trash, six tires, and even a refrigerator door from local riverbeds. Now in its 27th year, the Charles River Earth Day Clean-Up brings together more than 3,000 volunteers to remove litter and invasive species along 80 miles of the Charles River — protecting an important natural resource in our communities.


CRWA plays a vital role in protecting this treasured urban river for everyone to enjoy. Through community partnerships across the 308-square-mile Charles River Watershed, the work of the CRWA benefits about 1 million residents in 35 cities and towns, and we’re honored to support these efforts with both volunteers and a charitable grant.


We are privileged to partner with a community organization aligned with our commitment to sustainability that is making a big impact on river restoration and climate resilience. We hope you’ll visit the Charles River this spring and enjoy all it has to offer. 

Construction Update

Cambridge - Boston - Somerville

May 4 - May 16

City of Cambridge

Approved construction hours in Cambridge:


  • Monday to Friday from 7 a.m. to 4 p.m.
  • Occasional activities may be performed beyond these hours or on weekends based on approval from local officials.
  • Approved Saturday work hours:
  • 121 Broadway: 7 a.m. and 5 p.m.
  • Second Street: 7 a.m. and 5 p.m.
  • Daytime duct bank work on Memorial Drive is permitted Monday through Friday between 9 a.m. and 3:30 p.m.
  • Daytime vault installation on Memorial Drive is permitted Monday through Friday between 7 a.m. and 5 p.m.
  • Nighttime duct bank work on Memorial Drive is permitted Sunday evening through Friday morning between 8 p.m. and 5 a.m.

Underground Distribution Activities in Cambridge

  • Binney Street:
  • Crews are installing manholes and duct bank associated with electric distribution line work between Third Street and Sixth Street. This will continue for several months progressing towards Galileo Galilei Way.
  • Crews are installing duck bank at an additional work zone location on Binney Street within the sidewalk across from Fulkerson Street. This will require a pedestrian crosswalk detour; signage will be posted.

Underground Transmission Activities in Cambridge

  •  Broadway:
  • Crews are installing transmission line conduit within and beyond the new substation site at 121 Broadway. This activity is occurring off the roadway progressing towards Third Street, Monday through Saturday.
  • Galileo Galilei Way:
  • Crews have remobilized to install duct bank between Broadway and Main Street, where two vaults were installed last May. Lane restrictions will be necessary throught this activity.


  • Second Street: 
  • Crews continue excavating to support the installation of underground duct bank between Linskey Way and Athenaeum Street. This work will occur Monday through Saturday, utilizing temporary detours. Motorists seeking Second Street from Binney Street will be detoured and should follow posted signage. Delivery access to nearby loading docks will be maintained.
  • Ames Street: 
  • Crews are excavating to install underground vaults and duct bank between Main Street and Memorial Drive.
  • This work necessitates a 24/7 southbound traffic detour between Main Street and Memorial Drive. Motorists should follow posted signage.
  • Cyclist and pedestrian traffic has shifted to the west side of the road between Memorial Drive and Main Street.
  • Construction continues to necessitate a 24/7 road closure on Ames Street between Memorial Drive and Amherst Street. Motorists should continue to follow posted signage.
  • Northbound travel will be maintained between Amherst Street and Main Street, 24/7. Nothbound travel on Ames Street can be accessed via Amherst Street.
  • Memorial Drive / Massachusetts Avenue:
  • Daytime crews continue duct bank installation on Memorial Drive Monday through Friday, 9 a.m. to 3:30 p.m. Lane restrictions will be in place.
  • One crew is working near the Ames Street intersection.
  • Another crew is working near the Vassar Street intersection.
  • A third crew is working near Brookline Street progressing toward magazine Street.
  • Nighttime crews continue excavation and temporary restoration on Memorial Drive Sunday evening through Friday morning, 8 p.m. to 5 a.m. Lane restrictions will be in place.
  • One crew is working between Mass Ave. and Ames Street.
  • Another crew is working within the Mass Ave. ramps connecting to and from Memorial Drive.
  • Field tests, or test pits, are ongoing within the eastbound lane of Memorial Drive near Magazine Street during daytime hours.

 Traffic Configurations


  • Construction activities will generally be done utilizing lane restrictions or alternating lane traffic patterns. If detours are necessary, clear signage will be posted to direct motorists and cyclists. Please continue to check the project website for updates and postings of traffic plans.
  • Southbound travel on Ames Street remains closed 24/7 between Main Street and Memorial Drive. Southbound traffic on Ames Street continues to be detoured at Main Street, to Wadsworth Street and northbound traffic on Ames Street will remain open between Amherst Street and Main Street.
  • Westbound motorists on Binney Street seeking Second Street will be detoured to Third Street, then Linskey Way to connect to Second Street. Eastbound motorists will be detoured to First Street, then Linskey Way or Athenaeum Street to connect to Second Street.

City of Boston

Anticipated construction hours in Boston:


  • Monday to Friday from 7 a.m. to 4 p.m.
  • Occasional activities may be performed beyond these hours or on weekends based on approval from local officials.

Upcoming Construction Activities in Boston:

  •  Lincoln Street: 
  • Crews will conduct field tests, or test pits, along Lincoln Street between Franklin Street and Cambridge Street.
  •  Cambridge Street: 
  • Crews will conduct field tests, or test pits, along Cambridge Street between Lincoln Street and Windom Street.

City of Somerville

Anticipated construction hours in Somerville:


  • Monday to Friday from 7 a.m. to 5 p.m.
  • Occasional activities may be performed beyond these hours or on weekends based on approval from local officials.

Upcoming Construction Activities in Somerville:

  •  Charlestown Place: 
  • Crews are performing inspections at several manhole locations on Charlestown Place between Prospect Street and Milk Alley. Lane restrictions will be necessary to complete this work.
  •  Charlestown Street: 
  • Crews are conducting field tests, or test pits on Charlestown Street between Allan Street and Merriam Street. Lane restrictions will be necessary to complete this work.

Click the image below to view our

Interactive Project Map!

Visit the GCEP Website to learn more


Have a question about the Project or its approved routes? Please reply to this email with any questions or to setup a meeting.

Keeping You Informed

Eversource is committed to being a good neighbor and keeping you informed of Project progress.


Stay in Touch

Facebook  Twitter  Instagram  Youtube  Linkedin  
Address: 247 Station Drive
Westwood, MA 02090
Phone: 1-833-836-0302