Pouring on Progress
On April 16, GCEP accomplished a project milestone of installing the first underground vault on Linskey Way in Cambridge. On April 28, a second vault was installed on Linskey Way. Soon, crews will excavate to install duct bank conecting the two manholes.
The next vaults to be installed on the project will be off roadway at the corner of Broadway and Third Street at the Volpe parcel. There are 54 total vaults to install on GCEP.
|