Greetings Residents of Westfield

September 2023 - Newsletter 4

We are thrilled to bring you the latest updates on the construction activities happening within our community.


Construction has been advancing swiftly throughout the summer season. We trust that everyone enjoyed a fantastic summer and is now excited to be returning to school.

A video of images from the Westfield Elementary School construction site

A video of the progress photos at the Elementary School construction site during August 2023

As we welcome the arrival of September, our progress with the construction of the new elementary school remains strong. The project is staying firmly on track. For those of you in the vicinity of the site this month, here's a glimpse of the key developments that are ongoing:


Building Underground: Our construction team has been diligently working on building the foundation, including the critical underground components. This foundational work is essential for the stability and longevity of the entire structure.


Slab on Grade (SOG) Pour: On Monday, September 18th, we are scheduled to pour the Slab on Grade (SOG) for the center and kitchen areas. This marks a significant step towards the completion of these essential spaces within the building.


Roofing Progress: The roofing phase is well underway and progressing smoothly. We anticipate that the roofing work will be completed in approximately two weeks. This milestone will enhance the building's weather protection and overall structure.


Duct Work Installation: Our team is currently focused on installing ductwork in the North lower level of the building. This work is vital for the efficient circulation of air within the facility and ensures the comfort of occupants.


Roof Drain, Venting, and Water Piping: We are actively installing roof drains, venting systems, and water piping in the North section of the building. These components are crucial for maintaining the building's functionality and structural integrity.


CMU for Stairs C & D: Construction of CMU (Concrete Masonry Unit) for Stairs C and D is progressing according to schedule. These staircases are essential for safe and convenient vertical movement within the building.


Exterior Metal Stud Framing: We have initiated exterior metal stud framing in the North section of the building. This framing work not only reinforces the structure but also provides support for future exterior finishes.

Photos of construction progress in September 2023

These construction newsletters are developed and generated by the Owner's Project Manager, to keep the community informed of the progress being made on the site.


We understand that the construction process may cause minor inconveniences, such as temporary detours or noise disturbances. However, we sincerely appreciate your patience and understanding as we work towards creating a better future for our community.



As always, safety remains our utmost priority. We assure you that all necessary precautions are being taken to ensure a secure and controlled construction environment.

If you have any questions, comments, or concerns regarding the school construction project, please send an email to P3 and we will answer them as quickly as possible.



Email the Project Team

Join the Email List