Over the next few weeks, the work crews will pile the accumulated loam and begin the excavation of the retention basin for the storm-water recharge. The workers will also remove the unsuitable soils from the location of the actual structure.
Once these tasks are completed the contractor will begin the task of placing the foundation footings and the actual foundation. These tasks will take approximately a month.
While the site preparation progresses, the project manager, P3 and CBA will be busy approving every piece of material to be used. Each piece is submitted and then approved by the designers for quality conformance to the project specifications. The management team will verify that the materials used match the approved materials and that the quality of construction is on par with industry and specified standards.
We ask that you enjoy the construction of your new School from a safe distance. Please do not enter the construction site and be respectful of the workers, as we are asking that they are respectful guests of our community.
|