PAVING FOR PROGRESS
Johnson Avenue NW       

Construction Update: 6-22-18
Construction work continues to progress on Johnson Ave despite some wet weather recently.  Over the next few weeks, the contractor will continue installing new water main and storm sewer between Autumn Woods Dr and Wiley Blvd, and in the intersection of Johnson Ave and Wiley Blvd.

Starting on Tuesday, June 26, the intersection of Johnson Avenue and Edgewood Road NW will be reduced to one lane each direction for a separate project - to repair a manhole. That work is not expected to last more than a few days.

As always, thank you for your patience!