PAVING FOR PROGRESS
Northwood Drive Improvements        


Construction Update: 5-4-18
 

Crews continue to work on the water main installation along Northwood Dr. 

Important Traffic Notice
Starting on Monday, May 7, Glass Rd NE will be closed to westbound traffic at Northwood Dr NE for approximately 10 days to allow crews to tie into an existing water main. 

In the next few weeks, the new water main installation should be completed and crews will begin transferring water services to the new water main and storm sewer.  

Please watch for door hangers that provide notification to property owners about 24 hours in advance of temporary water service interruptions. 

As always, thank you for your patience!



Contractor 
Rathje Construction Co.
Brad Andes
319-330-7399

City Construction Inspector
Ron "McGee" Deitrich
319-521-5852
r.deitrich@cedar-rapids.org

City Construction 
Eric Bahl 
319-286-5531
e.bahl@cedar-rapids.org