Water main work will be wrapping up over the next few weeks.  There will be intermittent water service outages while remaining services are transferred to the new water main, and tying in the new main to the existing main.

The contractor will begin work on storm sewer in the middle of the project area, and work their way towards Glass Rd.  There will be temporary closures of driveways to place storm sewer, but they will be placing rock down to allow property owners to get in and out. 

Street removal and new paving is anticipated in about a month. 