PAVING FOR PROGRESS
14th Avenue SE       


Construction Update: 3-23-18
 
Construction continues on 14th Ave. 

Storm sewer installation was completed this week, and water main installation is anticipated to be completed in the next two weeks.

Over the next two weeks, there will continue to be brief water service outages as Rathje Construction transfers your old house service line over to the new water main.  

Coming Up

Street paving between 39th St and 42nd St, and  between 36th St and 38th St is expected to begin in mid-April, weather permitting.

We will continue to provide these updates as the project continues. 