PAVING FOR PROGRESS
C Avenue NE       


Construction Update: 8-9-17
 

Crews continue to work on a variety of improvements to C Avenue. They are currently working on sewer, curb and gutter, sidewalk ramps, the pavement, and some landscaping.

In the next two weeks, they anticipate laying new pavement between 40th Street and 42nd Street. 

Pavement markings have been placed between Collins Rd and Old Marion Rd.  Some sidewalk work remains to be completed on the east side.

The project is approximately 70% complete and is on schedule. 

Contractor 
Pirc Tobin Construction
Taylor Burgin
319-350-6019
City Construction Inspector
Jeremy Blok
319-775-3386