PAVING FOR PROGRESS
C Avenue NE       


Construction Update: 6-9-17
 
Crews completed the pavement work and painting at the intersection of C Avenue and Old Marion Road. The pavement markings you see in this area are temporary; once the final overlay is complete, permanent lane markings will be established. 

Work continues on the remaining portion of the project, including pavement, sewer/stormwater, water main, curb and gutter, and sidewalk/bike lanes.

Please continue to place your garbage and recycling containers in their usual location, so the contractor can coordinate their pick up. Thank you again for your ongoing patience. 