PAVING FOR PROGRESS
29th Street Drive SE       


Construction Update: 4-29-17
 

Roadway patching is continuing on the westbound lanes, along with storm water intake replacements. Crews are also working on curb and gutter, the sewer utilities, and driveway replacements. 

Starting next week, crews will begin working on the other side of the road to perform concrete patching and intakes; traffic flow will continue to be one way, eastbound only. 

As the contractor continues paving, driveways will be temporarily blocked. Crews will work to minimize these disruptions as much as possible.

Thank you for your patience as we continue this project!

Contractor 
Ricklefs Excavating LTD
Cory Elwick
319-480-8184

City Construction Inspector
Jason Junk
319-286-5724