PAVING FOR PROGRESS
29th Street Drive SE       


Construction Update: 5-11-17
 

Roadway work continues on the eastbounds lanes; traffic flow is still one way, eastbound only.  

Work this week includes pavement, sewer, and curb and gutter, which is similar to previous weeks. Residents' driveways will continue to be replaced - temporary access restrictions will be in effect during these times.

Starting next week, contractor crews will begin milling the new gutter section and replacing intakes.

Residents can continue to place their garbage and recycling containers in their usual spots, so the contractor can arrange for their pick-up. 

Thank you for your ongoing collaboration! 

Contractor 
Ricklefs Excavating LTD
Cory Elwick
319-480-8184

City Construction Inspector
Jason Junk
319-286-5724