Construction Update

August 6, 2024

Upcoming Activities

Due to delays in materials, no work is scheduled for the week of August 12.

Continuing Activities

For the remainder of the week, crews continue trenching and placing conduit in and near the three work zones to supply power to the signs. During this work, travel lanes and shoulders may be closed.


Motorists should reduce speed and be prepared for sudden stopping traffic within the work zone.


Area residents can expect an increase in noise, dust, and vibration during this work.

Project Overview

The Utah Department of Transportation (UDOT) will install three overhead variable message signs (VMS) and three traction warning signs on roadways that lead to the Cottonwood Canyons. Once installed, these signs will provide up-to-date traffic conditions in both Big and Little Cottonwood Canyon.


This information will assist motorists and visitors to the Cottonwood Canyons on the best location for parking and transit and ease traffic by providing early traffic information so motorists can make travelling decisions prior to entering the canyons.

Project Overview Map

Project Overview Map

Sign installation locations

6200 S Sign Map

6200 South sign locations

3200 East - Overhead

3300 East - Traction

9400 South sign map

Approx 1770 E 9400 S

Wasatch Blvd sign map

Wasatch Blvd sign locations

7650 South - Overhead

8000 South - Traction

Know before you go! Check UDOT Traffic before hitting the road. 

UDOT main logo

Contact the Team

This project has a dedicated Public Involvement Team to answer questions or concerns you may have throughout the duration of construction. If you are interested in joining our mailing list to receive weekly construction activity updates, please reach out to our team at the contact information below.


Project Hotline - 855-925-2801 Project #7135

Email - cottonwoodsigns@utah.gov

Project Website - www.udotinput.utah.gov/cottonwoodsigns