Construction Update

July 22, 2024

Upcoming Activities

As early as Thursday, July 25, crews will be drilling the sign base near 3200 East 6200 South for the overhead sign board.


As early as Friday, July 26, crews will pour concrete for the three traction device warning signs and the overhead sign board on 6200 South.


Between 8:00 a.m. and noon, crews will pour concrete for the three traction device signs - 3300 East 6200 South, 8000 South Wasatch Blvd, and 1850 East 9400 South. During this work, crews will close the shoulder area and right travel lanes.


Between noon and 2:00 p.m., crews will pour concrete for the overhead sign board near 3200 East on 6200 South. During this work, crews will close the eastbound acceleration lane exiting from Canyon Slope Square (near Bandits'). Motorists should be prepared to yield to traffic on eastbound 6200 South.


As early as Tuesday, July 30, crews will begin drilling activities and pouring concrete for the overhead sign boards near 7650 South Wastach Blvd and 1770 East 9400 South. During this work, crews will close the shoulder area and right travel lanes. Area residents can expect an increase in noise, dust, and vibration during this work.

Motorists should reduce speed and be prepared for sudden stopping traffic within the work zone.

6200 South Sign Location Map

Approx 3200 E 6200 S

Wasatch Blvd Sign location map

Approx 7650 S Wastach Blvd

9400 South Sign location map

Approx 1770 E 9400 S

Continuing Activities

Crews continue trenching in and near the three work zones for conduit to supply power to the signs.

Motorists should reduce speed and be prepared for sudden stopping traffic within the work zone.

Project Overview

The Utah Department of Transportation (UDOT) will install three overhead variable message signs (VMS) and three traction warning signs on roadways that lead to the Cottonwood Canyons. Once installed, these signs will provide up-to-date traffic conditions in both Big and Little Cottonwood Canyon.


This information will assist motorists and visitors to the Cottonwood Canyons on the best location for parking and transit and ease traffic by providing early traffic information so motorists can make travelling decisions prior to entering the canyons.

Project Overview Map

Project Overview Map

Know before you go! Check UDOT Traffic before hitting the road. 

UDOT main logo

Contact the Team

This project has a dedicated Public Involvement Team to answer questions or concerns you may have throughout the duration of construction. If you are interested in joining our mailing list to receive weekly construction activity updates, please reach out to our team at the contact information below.