Ohio Street I-90/94 Feeder Ramp Resurfacing
The Illinois Department of Transportation (IDOT) will be performing resurfacing work on the outbound lanes of the Ohio Street feeder ramp. Only two lanes will be closed at a time. The project is estimated to be in progress until late 2025.
676 North Michigan Avenue Façade Project
Redmond Construction was hired to complete a façade project at 676 North Michigan Avenue. Currently, the following closures are in-place:
- Sidewalk on the south side of Huron, from Michigan Avenue to a point 150' west thereof
- Curb lane on the south side of Huron, from Michigan Avenue to a point 150' west thereof is being used as a pedestrian walkway
- Partial sidewalk closure the west side of Michigan, from Huron to a point 100' south thereof
This project is expected to be completed by fall 2025.
State Street Bridge Project
On Monday, April 28, the Chicago Department of Transportation (CDOT) began emergency structural repairs to the State Street Bridge. Throughout the project, the bridge will be closed to vehicular and pedestrian traffic. State Street will remain open on both sides of the bridge during construction, and vehicles crossing the river will be rerouted to Clark Street and Dearborn Street.
The project is expected to be completed at the beginning of December 2025.
River North Lighting Project
The Chicago Department of Transportation (CDOT) has completed new light pole installation in the area bounded by Chicago, Ontario, Orleans, and the river. CDOT has begun removal of the old light poles and continues to restore infrastructure trenching.
Pin & Link Project on Randolph and Columbus
CDOT crews are scheduled to perform steel work and bridge expansion joint rehab along Randolph Street, Columbus Drive, and Stetson Avenue. Please see details below:
General Construction Schedule:
7:00am - 3:30pm, Monday - Friday; with the occasional extension to 5:30pm as needed.
Scope of Work and Access Impacts During Construction:
In general, one lane of travel will be open at all times along each roadway, level, and direction. Access along sidewalks will remain open with detours around the work areas.
This project is expected to be completed at the end of June 2025. Asphalt restoration will occur in July 2025.
Bally's Casino Caisson Pours
- Caisson pours are nearing completion and will be followed by foundation and utility work
- Total number of Casino and Hotel caissons: 356
- Casino Piles – a total of 202
Work hours will continue to be 8am-8pm. However, if an issue arises during a pour, there is the potential that crews will work past 8pm. Once a caisson pour begins, it cannot stop until it is finished.
|