In November, crews continued construction activities along the corridor:
Area 1 West: Reston Avenue to Baron Cameron Avenue:
- Started drilling for noise barrier foundations west of Reston Parkway along eastbound Route 7.
- Paving for the shared-use path along westbound Route 7 was completed between Utterback Store Road and Reston Parkway, and paving of the shared-use path along eastbound Route 7 between Markell Court and Crippen Vale Court began. The shared-use paths will remain closed until later in the project due to ongoing construction activities in these areas.
- Storm sewer installation west of Baron Cameron Avenue continued.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way:
- Continued noise barrier post and panel installation along eastbound Route 7 between Delta Glen Court and Colvin Forest Drive.
- Started installing posts for the combination noise barrier/retaining wall along westbound Route 7 between Colvin Run Road (east) and Colvin Run Road (west).
- Storm sewer installation between Baron Cameron Avenue and Colvin Forest Drive continued.
- Continued earth-moving activities at the intersection of Route 7 and Baron Cameron Avenue.
- Continued construction of the retaining wall between eastbound Route 7 and the Colvin Run stream channel.
- Construction of foundations for the piers and western abutment of the eastbound Route 7 bridge over Difficult Run continued.
- Continued drilling for noise barrier foundations along westbound Route 7 west of Towlston Road, and for the retaining wall at the intersection of westbound Route 7 and Towlston Road.
- Completed Stage 2A storm sewer installation, performed grading, and placed cement treated aggregate along westbound Route 7 between Towlston Road and Trap Road.
- Performed grading, placed cement-treated aggregate and base asphalt, and completed curb construction along westbound Route 7 between Lyons Street and Towlston Road.
- Continued paving and curb placement along westbound Route 7 between Towlston Road and Lewinsville Road.
- Completed the jack and bore storm sewer pipe crossing underneath Route 7 between Lewinsville Road and Laurel Hill Road.
Third-party utility design and relocation activities are also ongoing.
Click here to learn more on the design and construction schedule, environmental efforts, right of way, noise walls and other project details.