Cotton Belt/Silver Line Update (this is really long)
DART has postponed their bi-annual meeting with the community to February 9th, from 6:30-8:30 pm. The meeting will be held at the Texas A&M AgrilLife building, 17360 Coit Road.
Preston Green Park pedestrian bridge update - concrete pouring and construction continues. A new consultant for the park makeover is being hired.
Meandering Way upate - only one lane each direction remains open for vehicles. Construction continues.
Dickerson update - concrete pouring continues. This section is nearing completion.
Coit update - right lane closures to prepare for traffic signals at Alacasia, Sugar Cane and Osage continue.
Hillcrest update - vehicle traffic remains one lane each way - NEW: the permit for DART to begin drilling has been issued effective 1/23/23 for 12 weeks. After the 12 weeks, they will have a permit for another part of the project at Hillcrest. Here are details for the next 12 weeks:
Bridge Abutments, Pump Station, and Approach Slab Construction Narrative:
ATS will begin by installing the 60in drill shafts for Abutment #1 (west side of Hillcrest) and the adjacent 60in zone of influence retaining wall shafts from North to South followed by the 36in approach slab drill shafts. Drill shafts will remain buried after completion. Once the drill shafts are complete, ATS will move their rig to the east side to begin drilling of Abutment 2 (east side of Hillcrest), zone of influence shafts, and pump station drill shafts. AWH structure crews will begin construction of Abutment #2 & approach slab, upon completion of drilling activities. Urban Infraconstruction will then place the pedestrian bridge Abutment #2. All work will happen in linear fashion not concurrently due to spatial constraints.
Pedestrians will be shifted over to the southbound right lane closure and protected on each side by barrier and Crowdcades. This path will be ADA compliant.
Contractors Involved:
• Buyers Barricades – Setting of traffic control
• ATS Drilling – Install drill shafts
• AWH – Daily traffic control maintenance, construct track bridge abutment and approach slabs
• Urban Infraconstruction – Construct pedestrian bridge abutments
Start Date: 1/23/23
Duration: 12 weeks
Campbell update - NEW: the permit for DART to begin work at has been issued effective 1/30/23 through 7/6/23. Two lanes of traffic will remain open in each direction.
Limits of the pavement reconstruction will extend 160’ west of the proposed double track crossing and will include the reconstruction of the driveways at Bent Creek North Condominiums and Prestonwood Trail Apartments. East of the double track crossing, the limits of the pavement reconstruction extend approximately 275’. Pedestrian access with adequate lighting, drainage, and other safety provisions through one side of the construction zone will be maintained throughout the road closure. The proposed drainage at the Campbell Rd crossing includes removing 2 existing RCP culverts on either side of the track crossing and 3 inlets. The new design will replace these with an 18” class iv RCP culvert and 2 curb inlets 70’ east of rail crossing. Additionally, 2EA – type Y inlets will be replaced in the rail guideway north of the road that will tie into the existing 39” storm drain running under Campbell Rd. Wet utility modifications include relocating the existing 16” water main on the north side of Campbell and encasing it with “Class B+” embedment per the DWU drawing, which will protect these wet utilities under the 2 proposed Silver Line tracks. The proposed Campbell Road double track crossing will require franchise utility relocations by Explorer, Sprint & Qwest. The existing Sprint FOC west of the tracks and the existing Qwest FOC east of the tracks will require a relocation. Both existing FOC will be abandoned and will be relocated in a joint duct along the eastern side of DART’s ROW. The Explorer high pressure gas line will be relocated from the western side of the tracks to the eastern most side of DART’s ROW. All franchise utility relocations have been completed.
AWH proposes to construct the Campbell Road crossing under a multiple phased partial closure to allow for 2 lanes of traffic to be open in each direction at all times.
Pedestrian access around one side of the work area, and access to the residences on the southeast and northeast quadrants of the crossing will stay open throughout the entire duration of Campbell Rd crossing construction, which is noted in the TCP plans. Additionally, this construction will not be done concurrently with the proposed crossing work at Davenport East or Davenport West.
CROSSING CONSTRUCTION NARRATIVE: AWH proposes to construct the Campbell Road crossing under a 7-phase closure. AWH will follow the Dallas’ ILA work hours on weekdays from 7AM – 9PM and on weekends from 9AM – 7PM.
Initial Phase: Community Notification 1. Message boards will be set 2 weeks prior to work beginning, notifying the public of the upcoming lane closures.
PHASE 0: In Phase 0, AWH will install the new storm drainage RCP across Campbell Rd. AWH will use temporary lane closures to cut the pavement, excavate, and install the new storm drain. Road plates will be used to cover the excavation at the end of the day and lane closure will be removed. Road plates will be secured with asphalt each night. 1. Install necessary SWPPP items 2. Saw cut full width of pavement for proposed RCP alignment 3. Temporary lane closures set up for pavement removal, excavation, pipe install, and backfill. 4. Steel plate at end of day over excavated sections. 5. Repeat as pipe is installed across the roadway. 6. Install temporary asphalt.
PHASE 1: In Phase 1, the traveling public will be pushed to the 2 outside lanes in either direction. The inside lanes next to the median will be closed to construct the new profile of Campbell Road. MOT - 1. Set traffic control and advanced warning signage to close 1 inside lane in either direction on Campbell Road. The 2 outside lanes in either direction will remain open during phase 1 construction. CONSTRUCTION 1. Demolish and remove roadway pavement and median. 2. Remove existing, single-track crossing. 3. Rebuild track crossing subgrade for double track crossing. 4. Remove existing RCP east and west of the crossing. 5. Grade for new roadway profile. 6. Install systems cable under phase 1 concrete pavement. 7. Place and grade 8” subgrade 8. Place new 10” continuously reinforced concrete pavement. 9. Lay temporary asphalt in track guideway and median detour. 10. Switch traffic for phase 2 construction. ESTIMATED DURATION – 5 WEEKS
PHASE 2: In Phase 2, AWH will reconstruct the 2 outside eastbound lanes of traffic. Traffic will be reduced to 2 lanes of traffic in each direction between Davenport and Keller Springs. The 2 eastbound lanes will be split by the median via a detour at Keller Springs and return to normal traffic outside the east limits of construction. Access for the Bent Creek North Condominiums and Prestonwood Trail Apartments will remain open during the construction of this crossing and their respective driveway will be built in halves. MOT - 1. Set traffic control and advanced warning signage to close 2 outside east bound lanes on Campbell Road. CONSTRUCTION 1. Demolish and remove remaining roadway pavement and medians. 2. Remove the single-track crossing. 3. Remove remaining portion of the existing 18” RCP west of the crossing. Install remainder of proposed 18” RCP on the east end and inlet. 4. Install remainder of systems cabling under phase 2 concrete pavement. 5. Grade for new roadway profile. 6. Place 8” subgrade 7. Install driveway in halves at adjacent condominium and apartments 8. Set Signal foundations 9. Place new 10” continuously reinforced concrete pavement paving. 10. Rebuild track crossing subgrade for double track crossing. 11. Backfill curbs and grade for sidewalks 12. Pour new sidewalk. 13. Lay temporary asphalt in track guideway. 14. Install temporary striping until track work is completed. 15. Reset Phasing. ESTIMATED DURATION – 6 WEEKS
PHASE 3: In Phase 3 AWH will reconstruct the 2 outside westbound lanes of traffic. Traffic will be reduced to 2 lanes of traffic in each direction between Davenport and Keller Springs. The 2 westbound lanes will be split by the median via a detour after the Davenport intersection and return to normal traffic outside the east limits of construction. Access for the Bent Creek North Condominiums and Prestonwood Trail Apartments will remain open during the construction of this crossing and their respective driveway will be built in halves. MOT - 1. Set traffic control and advanced warning signage to close 2 outside westbound lanes on Campbell Road. CONSTRUCTION 1. Demolish and remove remaining roadway pavement and medians. 2. Remove the single-track crossing. 3. Perform Water line reroute and encasement 4. Remove remaining portion of the existing drainage line RCP. Install proposed RCP drain lines. 5. Install remainder of systems cabling under phase 2 concrete pavement. 6. Grade for new roadway profile. 7. Place 8” subgrade 8. Install driveway in halves at adjacent condominium and apartments 9. Set Signal foundations 10. Place new 10” continuously reinforced concrete pavement paving. 11. Rebuild track crossing subgrade for double track crossing. 12. Backfill curbs and grade for sidewalks 13. Pour new sidewalk. 14. Lay temporary asphalt in track guideway. 15. Install temporary striping until track work is completed. 16. Reset Phasing. ESTIMATED DURATION – 7 WEEKS
PHASE 4: Reconstruct Median In Phase 4, AWH will reconstruct the permanent median. Traffic will be reduced to 2 lanes of traffic in each direction between Davenport and Keller Springs. MOT - 1. Set traffic control and advanced warning signage to close 1 inside lane in each direction on Campbell Road. CONSTRUCTION 1. Remove temporary asphalt in median. 2. Grade medians. 3. Install gate foundations. 4. Pour median crossover and curbs 5. Backfill median curbs and seed 6. Rephase to full closure. ESTIMATED DURATION – 3 weeks
PHASE 5: Construct Track Crossing In Phase 5, a full closure will be needed to construction the track portion of the crossing. Traffic will either be diverted to Davenport Road (West) or McCallum Blvd. MOT - 1. Full closure within DART ROW on Campbell Road. CONSTRUCTION 1. Remove temporary asphalt in track guideway. 2. Regrade track subgrade. 3. Lay new rail and track panels across roadway. 4. Install asphalt headers. 5. Remove full closure and open to traffic. ESTIMATED DURATION – 3 DAYS
PHASE 6: Construct Hooded Left Turn Lane for Bent Creek North Condominiums In Phase 6, AWH will construct the hooded left turn lane for Bent Creek North Condominiums. Traffic will be reduced to 2 lanes of traffic in each direction between Davenport and Keller Springs. MOT - 1. Set traffic control and advanced warning signage to close 1 inside lane in each direction on Campbell Road. CONSTRUCTION 1. Remove temporary asphalt in median. 2. Grade medians. 3. Pour median crossover and curbs 4. Backfill median curbs and seed 5. Remove Traffic Control ESTIMATED DURATION – 1 weeks
|