Woodbury Demolition Slated for Late July
The Woodbury demolition is slated to begin in late July. The District, Gilbane Building Company and arborist Andrew Pratt, owner of The Dirty Horticulturist, LLC, are working to ensure that tree protection fencing is in place prior to the start of demolition. Abatement is complete in the gym, pool and west wing of the building. Abatement is ongoing in the east wing and the 1917 building (center of the Woodbury building that will be renovated). Mass demolition will begin with the pool, then move to the gym in August.
|